Davis Contractors Ltd v Fareham UDC

Davis Contractors Ltd v Fareham UDC
Court House of Lords
Full case name Davis Contractors Limited v Fareham Urban District Council
Decided 19 April 1956
Citation(s) [1956] UKHL 3, [1956] AC 696
Case opinions
Lord Reid
Court membership
Judge(s) sitting Viscount Simonds, Lord Morton, Lord Reid, Lord Radcliffe, Lord Somervell
Keywords
Frustration

Davis Contractors Ltd v Fareham Urban District Council [1956] UKHL 3 is an English contract law case, concerning the frustration of an agreement.

Facts

Davis Contractors agreed with Fareham UDC to build 78 houses over eight months for £92,425. It ended up taking 22 months, because Davis was short of labour and materials. It cost £115,223. Davis submitted the contract was frustrated, void, and therefore they were entitled to quantum meruit for the value of work done.

Judgment

The House of Lords held that although the performance of the contract had become more onerous it was not frustrated. Lord Reid argued that saying frustration was an implied term was fanciful, because people do not write about unforeseeable events. Instead he said the following.[1]

In my view, the proper approach to this case is to take… all facts which throw light on the nature of the contract, or which can properly be held to be extrinsic evidence relevant to assist in its construction and then, as a matter of law, to construe the contract and to determine whether the ultimate situation… is or is not within the scope of the contract so construed... appears to me that frustration depends, at least in most cases, not on adding any implied term but on the true construction of the terms which are, in the contract, read in light of the nature of the contract and of the relevant surrounding circumstances when the contract was made.

Lord Radcliffe concurred with the result.[2]

... There is, however, no uncertainty as to the materials upon which the court must proceed... [On the "officious bystander" test...] it might seem that the parties themselves have become so far disembodied spirits that their actual persons should be allowed to rest in peace. In their place there rises the figure of the fair and reasonable man. And the spokesman of the fair and reasonable man, who represents after all no more than the anthropomorphic conception of justice, is, and must be, the court itself. So, perhaps, it would be simpler to say at the outset that frustration occurs whenever the law recognises that, without the default of either party, a contractual obligation has become incapable of being performed because the circumstance in which performance is called for would render it a thing radically different from that which was undertaken by the contract. Non haec in foedera veni. It was not this that I promised to do.

argument that failed as well was that an express term was incorporated that the agreed price was binding only if there were in fact adequate supplies of labour and materials.

Australian Law

Lord Radcliffe's test was approved by the High Court of Australia in Codelfa.[3]

See also

Notes

  1. [1956] AC 696, 721
  2. [1956] AC 696, 728-9
  3. Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 337

References

External links

This article is issued from Wikipedia - version of the 2/8/2015. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.