Project Morpheus

For the virtual reality headset, see PlayStation VR. For other meanings, see Morpheus.
Project Morpheus

Logo of Project Morpheus
Country of origin USA
Last flight December 15, 2014[1]
Designer NASA
Manufacturer NASA/JSC
Application Planetary and lunar lander
Status Completed[2]
Liquid-fuel engine
Propellant liquid oxygen / methane[3]
Performance
Thrust 24000 N[4]
Specific impulse 321 s[5]
Burn time tested: 123 s[6]
Used in
Morpheus Lander
References
References morpheuslander.jsc.nasa.gov

Project Morpheus is a NASA project to develop a vertical takeoff and vertical landing (VTVL) test vehicle called Morpheus Lander in order to demonstrate a new nontoxic spacecraft propellant system (methane and oxygen) and an autonomous landing and hazard detection technology. The prototype planetary lander is capable of autonomous flight, including vertical takeoff and landings. The vehicles are NASA-designed robotic landers that will be able to land and take off with 1,100 pounds (500 kg) of cargo on the Moon.[7] The prospect is an engine that runs reliably on propellants that are not only cheaper and safer here on Earth, but could also be potentially manufactured on the Moon or Mars.[8][9] (See: In-situ resource utilization.)

The Alpha prototype lander was manufactured and assembled at NASA's Johnson Space Center (JSC) and Armadillo Aerospace's facility near Dallas.[7] The prototype lander is a "spacecraft" that is about 12 ft (3.7 m) in diameter, weighs approximately 2,400 lb (1,100 kg) and consists of four silver spherical propellant tanks topped by avionics boxes and a web of wires.[10][11][12]

The project is trying out cost and time saving "lean development" engineering practices. Other project activities include appropriate ground operations, flight operations, range safety and the instigation of software development procedures. Landing pads and control centers were also constructed.[7] From the project start in July 2010, about $14 million was spent on materials in the following 4 years; so the Morpheus project is considered lean and low-cost for NASA.[11][13] In 2012 the project employed 25 full-time team members,[14] and 60 students.[15][16] At any one time an average of 40 people worked on the project.[2] Project Morpheus devised and used streamlined processes and practices.[17] The Morpheus Lander's last flight was in December 2014. As there were no funds for further flights the lander was returned to JSC in February 2015.[18] Six formal documents were produced by the project. At the end of project review on March 12, 2015 it was estimated that $50 million had been saved by the lean development methods, minimising documentation, 'Beg and Borrowing' items and buying parts from home depot shops.[2]

Morpheus Lander in launch position

History

Project Morpheus started in July 2010 and was named after Morpheus, the Greek god of dreams.[19] The Morpheus spacecraft was derived from the experimental lander produced by Project M with the assistance of Armadillo Aerospace. Project M (NASA) was a NASA initiative to design, develop and land a humanoid robot on the lunar surface in 1000 days.[20] Work on some of the landers systems began in 2006, when NASA's Constellation program planned a human return to the Moon.[11]

In the same year 2006, Armadillo Aerospace entered the first Pixel rocket lander into the Lunar Lander Challenge part of NASA's Centennial Challenges.[21]

The Morpheus #1 Unit A test vehicle was first hot-fired 15 April 2011.[22]

Morpheus's new 4,200 pounds-force (19,000 N) engine[23] permitted NASA to fly longer durations by lifting more propellant into the air. The engine was upgraded again in 2013 to 5,000 lbf finally reaching 5,400 pounds-force (24,000 N).[4][24] A new design of landing gear was part of the Mechanical changes. NASA also replaced the avionics - this included power distribution and storage, instrumentation, the flight computer, communications and software. The enhanced landing system permits Morpheus, unlike the Pixels, to liftoff, fly, and land without help from a pilot.[25]

For Range Safety purposes the Morpheus#1 prototype falls into the category of guided suborbital reusable rocket.[26]:p. 11

In July 2012 the prototype lander was sent to the Kennedy Space Center for free flight testing and the media invited to view the Morpheus Lander.[27]

On August 9, 2012 the prototype Morpheus #1 Unit A (Alpha) lander crashed on take off, whilst performing its second untethered flight at Kennedy Space Center. No one was injured and no property was damaged but the vehicle was damaged beyond repair. The project investigated the cause and continued by building unit B.[28]

Autumn 2012 the Project Morpheus and ALHAT teams were combined.[6]

On February 7, 2013 the Project Morpheus team blogged that they have built the Morpheus 1.5B and 1.5C vehicles. The vehicles underwent a series of static hot fire and dynamic tethered flight tests at Johnson Space Center spring 2013 in preparation for a return to free-flight testing at Kennedy Space Center later that year.[6][29]

Project Morpheus: Testing of the NASA HD4 main rocket engine at NASA's Stennis Space Center[30]

On May 1, 2013 the replacement Morpheus #1.5 Unit B testbed was Hot Fired at the Johnson Space Center. The replacement's enhancements include a 5,400 pounds-force (24,000 N) thrust main engine and integrated oxygen/methane reaction control system (RCS), making it the first oxygen/methane vehicle with Main and RCS engines drawing propellant from the same tanks and first vehicle to use a cryogenic RCS system.[4][24]

On June 14, 2013 rapid re-usability was demonstrated by having two flights using the same lander on the same day.[31]

In July 2013 the ALHAT equipment was integrated into and tested with the lander.[32]

On September 26, 2013 the vehicles performed 20 short engine firings at a variety of conditions whilst fastened to the ground.[33]

In November 2013 the Bravo Lander was taken to Kennedy Space Center (KSC), Florida for free flight testing.[34][35] $750,000 of parts were purchased to make the replacement lander. KSC limited the noise vibrations on the lander as it lifts off by designing a mobile launch pad with a built in flame trench.[16]

Free Flight 9 on March 11, 2014 was the final flight before integration of ALHAT sensors on Bravo vehicle.[36] Free Flight 14 on May 28, 2014 was performed at night with the ALHAT acting as the prime guidance system. The hazards in the hazard field were automatically avoided.[37]

In May 2014 The NASA Project Morpheus formed part of the reference material for NASA's Lunar CATALYST initiative.[38]

A paper was published in 2013 revealing the lessons learnt during the development, which may be useful to future projects.[39] In 2014 a paper describing the integrated test campaign, including the free flights, was published.[40]

An article giving a short history of the project was printed in RocketSTEM in July 11, 2014.[41]

In November 2014, the Morpheus Lander was fitted with additional ALHAT sensors. The new optics permit the Navigation Doppler Lidar to accurately measure the vehicle's velocity relative to the ground.[42]

Objectives

The primary objectives of the Morpheus project were to demonstrate:

Specifically, the Morpheus project and the Autonomous Landing Hazard Avoidance Technology (ALHAT) project provide technological foundations for key components necessary to transport humans beyond low Earth orbit.[7]

The testbed can optionally be fitted with up to 1000 lb cargo, facilitating the 400 pounds (180 kg) Autonomous Landing Hazard Avoidance Technology (ALHAT) equipment permitting landings without operator interaction.[10][44] ALHAT permits the lander to fly to a specified location with high accuracy and to automatically avoid hazards including slopes greater than 5 degrees and boulders taller than 30 cm.[45]

In June 2013 the team remarked the potential to scale the 500 kg payload lander up to produce one able to land a habitable module with a crew on places such as the Moon.[46]

Hardware specifications

Morpheus Lander
Description Size Ref
Payload 500 kg [7]
Dry mass ~1100 kg [10]
Propellant methane/LOX [3]
Propellant mass 2900 kg [3]
Propellant tanks 4 off [11]
Pressurization helium [7]
Height 3.7 m [12]
Diameter 3.7 m [12]
Main Engine HD5 [6]
Primary RCS propellant methane/LOX [24]
RCS thrust 22–67 N [47]
Backup RCS propellant helium (He) [48]
Optional hardware ALHAT [44]
Class of lasers in ALHAT IV [49]
Morpheus Engine (HD5)
Description Size Ref
Thrust 24000 N [4]
Specific Impulse 321 s [5]
Maximum burn (tested) 123 s [6]
Propellant methane/LOX [3]
Throttle range 4:1 [4]
Fuel mixture ratio (TBD) -
Nozzle ratio (TBD) -
Air startable yes [50]
Engine restartable yes [31]
[33]
Maximum service life (TBD) -
Weight (TBD) -
Chamber pressure (TBD) -
Manufacture NASA JSC [7]
Minimum ground to nozzle during ignition ~15 feet [40]
Manufacturing cost per engine (2013) $60,000 [2]

The Project Morpheus vehicle 'Morpheus' is a full scale vehicle that NASA intends to be capable of landing Robonaut or a similar sized payload to the lunar surface. The spacecraft will perform all propellant burns after the trans lunar injection.[7] [51]

Navigation is completely autonomous from Lunar Orbit to touchdown. Navigation updates come from TRN Laser altimetry and star trackers after deorbit burn. Deep space navigation relies on radiometric and star trackers.[52]

To save money and time the prototype Morpheus landers are "single-string" prototypes, this means that unlike a spacecraft rated for actual space flight they do not have redundant systems. The exceptions are stated below.[14]

Morpheus #1.5 Unit A

Commands can be sent using separate Ultra High Frequency (UHF) radios to the thrust termination system (TTS). Use of the TTS by range safety will close two motorized valves which shut off the flow of liquid oxygen and methane to the engine - thereby terminating engine thrust. These TTS valves are completely independent from the rest of the vehicle systems. The TTS also stops the laser in the ALHAT's Hazard Detection System from firing - since Type IV lasers are not eye safe.[5][57]

For further details see the "Morpheus: Advancing Technologies for Human Exploration" paper.[5]

Morpheus #1.5 Unit B
The Morpheus Lander's main engine over the mini Flame Trench at the NASA Johnson Space Centre

The prototype Morpheus #1 Unit B lander is using the same design as the prototype Morpheus #1.5 Unit A lander with the following changes:[14]

Morpheus #1.5 Unit C

The prototype Morpheus #1 Unit C lander is using the same design as the prototype Morpheus #1.5 Unit A lander with the following changes:[14]

Autonomous Landing Hazard Avoidance Technology

The optional Autonomous Landing Hazard Avoidance Technology (ALHAT) equipment permits landings without operator interaction.[44] ALHAT permits the lander to fly to a specified location with high accuracy and to automatically avoid hazards including slopes greater than 5 degrees and boulders taller than 30 cm.[45] The active sensors include a flash LIDAR, a lidar Doppler velocimeter and a laser altimeter.[49][61]

Software

The Morpheus Control Room preparing to launch the Lander.

Project Morpheus lean development philosophy resulted in a mix of new and previously existing software being used. Software is used in:

Test bed tests

Hazard field at the end of the Shuttle runway KSC
2011

As of April 2011 the primary focus of the test bed is to demonstrate an integrated propulsion and inertial-based guidance, navigation, and control (GN&C) systems that can fly a lunar descent profile, thereby exercising the Autonomous Landing and Hazard Avoidance Technology (ALHAT), safe landing sensors and closed-loop flight control system.[43]

Additional objectives include technology demonstrations such as tank material and manufacture, reaction control thrusters, main engine performance improvements, Helium pressurization systems, ground operations, flight operations, range safety, software and avionics architecture.[7]

The Vertical Test Bed (VTB) Flight Complex at JSC has been successfully using the Mission Control Technologies (MCT) software written at NASA Ames to control the test flights of the Morpheus lander. Parameters displayed include propellant tank pressures.[69]

A set of integrated vehicle test flights including hot-fire, tethered hover tests and untethered “free-flights” were devised for the Morpheus vehicle.[5]

To provide clearance for the vehicle's exhaust plume during hot-fire tests the lander was tethered 20 feet (6.1 m) above the ground. A height of 15 feet (4.6 m) was used for the tethered testing.[40]:p. 4

The testing, test results and equipment modifications performed during 2011, up to and including Tethered Test 6, were published in the conference proceeding of the 2012 IEEE Aerospace Conference at Big Sky, MT[70]

2012

Videos of the test flights have been posted on the Morpheus Lander Channel on YouTube. This includes the 2012 regression test flights with the more powerful V1.5 engine whilst the lander is tethered, and the problematic early test flight that shows "This is why we test".[71]

On May 10, 2012 the testbed passed its hover and soft abort tests, shown in video "Morpheus Tether Test 15".[71] The lander was returned to the workshop to have the ALHAT equipment fitted. The Reaction Control System (RCS) thrusters were also fitted.[72][73]

During the Summer 2012, the Morpheus Lander V1.5 Unit A was transferred to the Kennedy Space Center in Florida for an untethered flight testing. Also, a "hazard field" was built containing hazards such as rocks and craters built at the end of the Space Shuttle's runway to test that the ALHAT system can automatically navigate to a clear landing site.[74] As can be seen in the photograph, the Kennedy's wide open spaces permit the entire flight path including runway and hazard field to be surrounded by a fire break consisting of a moat filled with water.

The 330 by 330 ft (100 by 100 m) hazard field included five potential landing pads, 311 piles of rocks and 24 craters that mimic an area on the Moon's south pole.[11]

On July 20, 2012, the 43rd anniversary of the Apollo 11 lunar landing, the Morpheus test vehicle arrived at Kennedy Space Center (KSC) for advanced testing. The high performance HD5 version of the Morpheus engine was performance tested at the Stennis Space Center in the summer of 2012. The testing and building of the hazard field were paid for by NASA's Advanced Exploration Systems Program (AES).[53]

2013

During Autumn 2012 and early 2013 a fourth and a fifth generation Morpheus methane/LOX rocket engine were test fired at Stennis Space Center. A successful long duration burn lasted 123 seconds. Other tests verified capabilities and throttle levels.[6]

The ALHAT equipment was tested using a helicopter on the KSC hazard field. Multiple flights were made using Morpheus like trajectories, which had to take wind direction into account.[6]

Fuel tanks for the lander were put through a series of inspections and tests, including checking welds for defects and cycling tank pressure to establish a minimum cycle life expectancy of the tanks. The maximum pressure capability was verified by pressurizing a sacrificial tank until it burst.[6]

The Morpheus team prepare the Bravo Lander for a test flight

On May 1, 2013 at JSC the replacement Unit B Morpheus testbed was fired for 50 seconds whilst fully tethered. The integrated methane reaction control system (RCS) and thrust vector control (TVC) jets were also fired. Many enhancements had been incorporated into the vehicle and ground systems.[24]

On May 16, 2013 at JSC the testbed was fired whilst fastened to the ground, and later tethered 3 ft (0.91 m) above the ground, followed by some reaction control system tests. A small leak was repaired, allowing the testing of the effects of vibration to be nominal. In preparation for the tests, the fire break around the test area had been paved and a mini "flame trench" dug.[50][75]

On May 24, 2013 at JSC the V1.5B testbed was high tethered. There was a good ignition and climb. A soft abort terminated the flight when the vehicle exceeded an internally set boundary limit whilst attempting to stabilize itself.[58]

On June 6, 2013 at JSC in Tethered Test 22 a tethered testbed successfully flew for 74 seconds. The hover lasted 60 seconds and was smooth.[76] Used the primary IMU.[77]

On June 11, 2013 in a tethered test at JSC the backup Inertial Measurement Unit (IMU) passed its flight test. The flight lasted 27 seconds including 17 seconds hovering.[77]

On June 14, 2013 two tethered flights were performed. The first firing was soft aborted when the vehicle exceed its safety zone due to an imbalance in the fuel load. The 2nd firing was successful. This counts as a restarting of the engine. During the second flight, the vehicle successfully switched from using its primary Inertial Measurement Unit (IMU) to the secondary IMU.[31]

On July 2, 2013 integration tests were performed with an ALHAT attached to the Morpheus Lander. These tests included "tilt" tests where the lander's legs were raised on different heights of blocks so the attitude is off vertical.[78]

On July 11, 2013 the first tethered flight test of Morpheus vehicle "Bravo" with Autonomous Landing & Hazard Avoidance Technology (ALHAT) laser sensors integrated on top was performed. On the second attempt there was a good ignition, but during ascent the vehicle translated downrange and exceeded the internally set range safety boundary limit (+/−4 m) for tether tests, triggering an automatic soft abort.[32]

On July 23, 2013 Tethered Test 26 was successfully performed. The lander and ALHAT flew to and hovered at two different heights. Both the primary RCS (methane/LOX) and the backup RCS (He) were used, producing a successful 'landing' at the end of the tether. Lateral excursion was a maximum of only ~0.2 m. The ALHAT's tracking and imaging were nominal, managing to identify the hazard target.[48]

On July 27, 2013 the combined Morpheus/ALHAT Tethered Test 27 worked. The lander took off, performed ALHAT imaging and then a lateral translation.[79]

On August 7, 2013 Tethered Test 28 was successfully performed. In a flight lasting ~80 seconds the vehicle executed an engine ignition, ascent, a 3-meter lateral translation over simulated Mars soil, 40 seconds of hover at the apex, and a slant descent to "landing" using free flight guidance. The Mars simulated soil was provided by Jet Propulsion Laboratory (JPL) as part of a plume study.[80]

On August 23, 2013 Bravo lander successfully performed Tethered Test 29 at JSC. During the ~50 second flight Bravo's actions included ignition, ascent and a 3-meter lateral translation. There was a 10 seconds hover at the apex, and a slant descent to the crane "landing" using free flight guidance.[81]

On August 29, 2013 Bravo lander successfully performed the ~63 second Tethered Test 30 flight at JSC. After an ascent of 5 meters with 15 seconds of hover at the apex, a 3-meter backwards lateral translation was performed. Followed by another 15 seconds of hover, and a forward slant descent.[29]

On September 18, 2013 in strong winds, the Bravo lander successfully performed Tether Test 31. This flight was a quick turnaround after the previous day's testing had been scrubbed. Various problems were solved by the team.[60]

On September 24, 2013 the Lander was launched from the ground. Several problems were detected resulting in an abort. The problems included a false "engine nozzle burn-through" alert and engine startup instability. On September 26, 2013 test HF10 was performed. This involved 20 short firings of the engine on the same day at a variety of pressures, temperatures and power levels. The investigation aimed to probe the instability boundaries of the engine during startup.[33][82]

The first successful free flight of the Project Morpheus lander. The flight took place at Kennedy Space Center on Tuesday December 10, 2013

On October 29, 2013 the lander and its rocket engine methane/LOX performed six off 600 ms burns whilst on top of the trench at JSC. There were no instabilities.[83] On November 1, 2013 with all the software and hardware enhancements included, the lander successfully performed a tethered flight test. The vehicle performed an air start whilst being supported by the tether.[84] On November 7, 2013 the project completed testing the lander at JSC with a Ground Test Takeoff and Landing (GTAL). The vehicle flew nominally and landed within 1 in (2.5 cm) cross range and 6 in (15 cm) downrange of its intended target. The GTAL test characterized the performance of the vehicle in lifting off from launch stands on the ground, flying to a height of 21 ft (6.4 m), hover and descent profile, and landing back on the ground at a separate pad 10 ft (3.0 m) from its launch point. This suggests that the faults revealed by Incident 2 below on August 9, 2012 have now been found and fixed.[35][85]

On December 6, 2013 the integrated vehicle passed Tether Test 33 at Kennedy Space Center in Florida. This was a repeat of Tethered Test 29. The test was primary performed to verify that the Bravo lander was OK after being transported from Texas.[86] On December 10, 2013 the first free flight of a Morpheus prototype lander was successfully conducted at Kennedy Space Center's Shuttle Landing Facility. The 54-second test began with the Morpheus lander launching from the ground over a flame trench and ascending approximately 50 feet, then hovering for about 15 seconds. The lander then flew forward and landed on its pad about 23 feet from the launch point and about 6 inches from the target point.[16][87][88]

On December 17, 2013 the Morpheus Lander successfully performed Free Flight 4. The preplanned trajectory was flown flawlessly, landing within 3.5 inches of its intended target. Morpheus ascended from the ground over the flame trench to an altitude of about 164 feet (50 m), after pausing briefly at 82 feet (25 m) to maintain the target ascent velocities. The vehicle then flew forward, covering about 154 feet (47 m) in 30 seconds, before descending and landing on a dedicated landing pad inside the ALHAT hazard field.[89][90]

2014

On January 16, 2014 Free Flight 5 was successfully performed at the KSC Shuttle Landing Facility. The Bravo vehicle flew higher and faster than in all of its previous flights. The preplanned trajectory involved ascending quickly to 57 m (187 ft), traversing 47 m (154 ft) while descending, then landing approximately 11 inches from intended target in the Hazard Field about a minute after launch.[91] On January 21, 2014 Bravo performed Free Flight 6. In a flight lasting 64 seconds the vehicle ascended to 305 ft (93 m) and then flew forward 358 ft (109 m) in 25 seconds. As planned, Bravo landed in the Hazard Field, 0.38 m (15 inches) from the target. The maximum ascent velocity was 11.4 m/s (25.5 mph).[92]

On February 10, 2014 Free Flight 7 was flown at KSC. Bravo flew to 467 feet (142 m) altitude and then traversed 637 feet (194 m) in 30 seconds before landing in the hazard field. The vehicle flew its pre-planned trajectory flawlessly, reaching a maximum ascent velocity of 13 m/s, and landing an on its intended target 74 seconds after launch.[93] The engineers state the altitude during tests is not the important part, but the flight experience gained, including all phases of the check-out, ground loading, flight, and recovery operations.[8]

On February 14, 2014 and March 3, 2014 hot fire testing of the lander's Roll Control System (RCS) using a variety of short and long pulses was performed at KSC.[94][95] The multi-center Morpheus Team successfully completed Free Flight 8 at the Kennedy Space Center (KSC) Shuttle Landing Facility (SLF) on Wednesday, March 5, 2014. Bravo vehicle flew to an altitude of 467 ft (142 m) and then traversed 637 ft (194 m) in 36 seconds, including diverting course mid-flight, before landing in the hazard field 56 ft (17 m) from its original target (simulating hazard avoidance). The vehicle reached a maximum ascent velocity of 13 m/s, and landed approximately 10 inches from its intended target 79 seconds after launch.[96]

On Tuesday, March 11, 2014 the Morpheus team successfully completed Free Flight 9 (FF9) at the KSC SLF. This was Morpheus' highest (177 m (581 ft), higher than the VAB & Washington Monument), fastest (13.4 m/s (30 mph) vertical & horizontal) and farthest (255 metres (837 ft)) flight to date.[36]

During the rest of March 2014 the ALHAT hardware was inserted again permitting a successful tethered test of the assembly on March 27, 2014. Tether Test 34 flight trajectory was similar to TT33 and TT29 with two hovers and a 3 metres (9.8 ft) translation during a 3.25 metres (10.7 ft) ascent.[97] Free Flight 10 (FF10) took place on April 2, 2014 with the ALHAT in open loop mode. The ALHAT imaged the Hazard Field and calculating navigation solutions in real time. Morpheus ascended to a maximum altitude of about 804 feet (245 m), then flew forward and downward initially at a 30-degree glideslope, then levelling out, covering a total of about 1334 feet (406.5 m) horizontally in 50 seconds while diverting to a landing site location 78 feet (23.8 m) from its initial target, before descending and landing on a dedicated landing pad at the front (south) of the ALHAT Hazard Field. The total flight time was ~96 sec, the longest flight to date.[98] Free Flight 11 on April 24, 2014 was a repeat of Free Flight 10 with some changes to the ALHAT.[99] April 30, 2014 Free Flight 12 was a repeat of FF10 but with the ALHAT choosing the landing location.[100]

On May 22. 2014 in Free Flight the ALHAT determined a safe location in the hazard field the landing location and flew the lander to it.[101]

The Morpheus/ALHAT team successfully completed Free Flight 14 (FF14) at the KSC SLF on Wednesday, May 28, 2014, Bravo's 12th and ALHAT's 5th free flight—and the first ever night flight. Initial data indicated nominal performance of all vehicle systems. The ALHAT Hazard Detection System (HDS) performed well, but identified a safe site just 0.5 metres (1.6 ft) outside the conservatively established limits around the center of the landing pad. ALHAT then navigated the vehicle in closed-loop mode through the entire approach, with the vehicle taking over navigation during the descent phase of the trajectory when ALHAT was already dead-reckoning. Had less conservative position error limits allowed ALHAT to continue to navigate to landing, the vehicle still would have landed safely on the pad.

The team overcame a few preflight issues, including a failed ignition due to a non-critical temperature exceeding its limit, which was corrected for the successful second attempt.[37]

On November 19, 2014 tested the Morpheus Lander at KSC. The ALHAT hardware had been enhanced with new optics that permit the Navigation Doppler Lidar to accurately measure the vehicle's velocity relative to the ground.[42] The test was aborted due to a fault in the remote control system. So far the engine has burnt for a total of 1,134 seconds.[102] Tether Test 36 (TT36) at the KSC SLF on Tuesday December 2, 2014 was a regression test. The Bravo vehicle followed its planned 40 sec trajectory flawlessly, although a handful of discrepancies were identified. The data was reviewed to assess these anomalies and ensure the vehicle and ground systems were ready to support a free flight test.[103]

On December 15, 2014 the prototype lander soared 800 feet above the north end of the Shuttle Landing Facility at Kennedy Space Center in Florida on free flight test No. 15. During the 97-second test, ALHAT, surveyed the hazard field for safe landing sites, then guided the lander forward and downward to a successful landing.[1]

Current

As of February 2015 planned testing has been completed. The lander was taken back to JSC.[18][104] The project review, including testing, was held on March 12, 2015.[2]

Test equipment and ground operations

In addition to the normal engineering tools several items of test equipment was made or procured. These include cranes wrapped in shielding against heat and debris,:p. 2 a tether, a bungee to control the tether:p. 7 and an energy absorber. The energy absorber was a metal tube filled with a fire proof aluminium honeycomb.[40]:p. 3

Concrete launch and landing pads were built. At Kennedy Space Centre a small flame trench for ground launches was dug near the hazard field (constructed to test the ALHAT). Cameras and recording equipment were installed. Computers and radio communications equipment used.[40]

Trolleys to move the lander, batteries and consumables were used. Safety clothing and eye protection against Category IV LASERS were issued.[57][105]

On a typical test day the ground operations staff work about 10 hours from roll-out until Morpheus is back in the hangar. The different portions of the day are Safety Brief & Vehicle Rollout, Pre-Fill Checkout, Propellant Load (Liquid Oxygen and Liquid Methane), Leak Check, Final Preparation, Flight, and Post Test. Activities are divided between the Pad Crew and the Control Centre. As well as the lander electrical batteries for ground power, cranes, load cells and propellant tankers need rolling out to the launch stands.[57]\\

Collaborations

NASA's Johnson Space Center collaborated with several firms, academic installations and other NASA centers whilst building and testing the Alpha and Bravo prototype Morpheus landers.

"For Morpheus and ALHAT, JSC has partnerships with Kennedy Space Center (KSC) for flight-testing; Stennis Space Center (SSC) for engine testing; Marshall Space Flight Center (MSFC) for engine development and lander expertise; Goddard Space Flight Center (GSFC) for core flight software development; and Langley Research Center (LaRC) and the Jet Propulsion Laboratory (JPL) for ALHAT development. Commercial partnerships with enterprises such as Jacobs Engineering, Armadillo Aerospace, Draper Labs, and others have augmented the development and operation of many aspects of the project."[106]

Health and safety issues

Although the liquid oxygen/liquid methane bipropellant mix is considerably easier and safer to handle than hydrazine, the propellants can catch fire and cryogenic fuel tanks and Dewars can explode.[105][107]

Incidents

Morpheus lander crash on August 9, 2012.
  1. On June 1, 2011, a test of the Morpheus lander caused a large grass fire on the grounds of the Johnson Space Center. A minor incident: no one was injured and the Lander was fine.[108] Subsequently a 10 ft (3.0 m) wide fire break was dug around the test area to prevent the spread of any possible grass fires.[109]
  2. On August 9, 2012, the lander tipped over, crashed, caught fire, and exploded twice during its initial free-flight test at the Kennedy Space Center.[107] The fire was extinguished after the tanks had exploded. No one was injured but the vehicle was not in a recoverable condition.[14] Following the accident about 70 different upgrades to the vehicle design and ground systems were made including adding some redundant instrumentation and mitigating the launch vibroacoustic environment.[24] Military-grade cable connectors and bus couplers have been fitted to the replacement vehicles as well as creating a flame trench on the launch-pad to reduce vibration.[59] A paper acting as an investigation report was published at the American Institute of Aeronautics and Astronautics: SPACE 2013 conference.[110]

Status

The Morpheus prototype liquid oxygen and methane (LOx/Methane) propulsion system demonstrated advantages in performance, simplicity, reliability, and reusability. [111] LOx/Methane provides new capabilities to use propellants that are manufactured on the Mars surface for ascent return and to integrate with power and life support systems. It was determined that Lox/Methane is extensible to human spacecraft for many transportation elements of a Mars architecture. The propellants provide significant advantages for reliable ignition in a space vacuum, and for reliable safing or purging of spacecraft.

The Morpheus lander flight demonstrations led to the proposal to use LOx/Methane for a Discovery Program mission, named Moon Aging Regolith Experiment (MARE) to land an in-situ science payload for the Southwest Research Institute on the lunar surface.[111]

See also

Notes

a. ^ Methane is an environmentally friendly (i.e. non-toxic) propellant that NASA hopes will reduce transportation costs by being made in-situ (ISRU). For instance, the Sabatier reaction could be used to convert carbon dioxide (CO2) found on Mars' atmosphere into methane, using either found or transported hydrogen, a catalyst, and a source of heat. Hydrogen can be made from water ice, which occurs on both the Earth's Moon and Mars.[8]

References

  1. 1 2 "Morpheus Soars in Free Flight 15". www.youtube.com. NASAKennady. Retrieved December 16, 2014.
  2. 1 2 3 4 5 Chris Bergin (March 14, 2015). "NASA dreams of future Morpheus project templates". NASA Spaceflight.com. NASA. Retrieved March 22, 2015.
  3. 1 2 3 4 5 6 7 "webpage A Visit With Morpheus by Jim Hillhouse, April 14th, 2011". AmericaSpace.
  4. 1 2 3 4 5 6 7 8 Robert L. Morehead, John C. Melcher (July 28, 2014). "Combustion Stability Characteristics of the Project Morpheus Liquid Oxygen / Liquid Methane Main Engine" (PDF). Conference Paper from AIAA/ASME/SAE/ASEE Joint Propulsion Conference; 50th; 28-30 Jul. 2014; Cleveland, OH; United States. Retrieved September 29, 2014.
  5. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Jon B. Olansen, PhD; Stephen R. Munday; Jennifer D. Mitchell; Michael Baine, PhD (May 23–25, 2012). "Morpheus: Advancing Technologies for Human Exploration" (PDF). Global Exploration Conference. GLEX-2012.05.2.4x12761.
  6. 1 2 3 4 5 6 7 8 "Hard at Work - February 2013". Project Morpheus : Blog. NASA - Project Morpheus. Retrieved February 8, 2013.
  7. 1 2 3 4 5 6 7 8 9 10 11 "Morpheus Lander Website's Home Page". NASA. Retrieved October 25, 2011.
  8. 1 2 3 "Innovative Partnership Tests Fuels of the Future". NASA. October 13, 2009. Retrieved March 3, 2012.
  9. Nasa's new Mars landing craft Morpheus bursts into flames on take-off. The Telegraph 10 August 2012.
  10. 1 2 3 4 "Equipped with New Sensors, Morpheus Preps to Tackle Landing on its Own". NASA website. NASA. Retrieved April 24, 2014.
  11. 1 2 3 4 5 Dean, James (August 2, 2012). "Morpheus lander prototype ready for KSC tests". Florida Today. Retrieved August 2, 2012.
  12. 1 2 3 4 "Morpheus Lander Twitter postings on January 21, 2014 (reply)". Twitter - Morpheus Lander. NASA. Retrieved January 21, 2014.
  13. Thom Patterson (May 19, 2014). "A father-son chat leads to first-of-its-kind NASA spacecraft". CNN. Retrieved May 19, 2014.
  14. 1 2 3 4 5 6 7 Moskowitz, Clara (September 14, 2012). "NASA pushes ahead with new prototype of Moon lander". Space.com. Retrieved September 19, 2012.
  15. "NASA Advisory Council briefing by Advanced Exploration Systems on November 15, 2012" (PDF). NASA. Retrieved February 5, 2013.
  16. 1 2 3 Dean, James (December 10, 2013). "Prototype Morpheus lander completes test flight at KSC". Florida Today. Retrieved December 12, 2013.
  17. Hart, Jeremy J., Devolites, Jennifer L. (September 10, 2013). "The Tailoring of Traditional Systems Engineering for the Morpheus Project". Conference Paper JSC-CN-29415. NASA. Retrieved April 18, 2014.
  18. 1 2 James Dean (February 22, 2015). "SpaceX nearing commercial satellite launch". Florida Today. Gannett Company. Retrieved February 22, 2015.
  19. Brandi Dean. "Project Morpheus Begins to Take Flight at NASA's Johnson Space Center, update dated 2nd May 2011". by NASA on its NASA.GOV website.
  20. Boyle, Alan (2011-07-01). "Inside NASA's 'Skunk Works' lab". MSNBC. Retrieved 16 July 2011. Project Morpheus started out as "Project M", a concept that called for landing a humanoid robot on the Moon in 1,000 days. Then reality set in, and the project was redefined.
  21. Young, Kelly (October 13, 2006). "Mock lunar landers to go head-to-head in X Prize Cup". New Scientist. Retrieved June 28, 2012.
  22. "The Project Morpheus Lander JSC2011-E-032040 (14 April 2011)". NASA. Retrieved May 8, 2013.
  23. 1 2 "YouTube video from NASAExplorerSchools1 called "NASA Now Minute: Forces and Motion: Project Morpheus" released Feb 27, 2012". NASA and YouTube.
  24. 1 2 3 4 5 6 7 8 "And So We Begin Again". NASA. Retrieved May 8, 2013.
  25. Keith Cowing (April 20, 2011). "Morpheus Lander: Cool Stuff That JSC PAO Won't Let You See - plus the MBaine comments".
  26. "2011 NASA Range Safety Annual Report" (PDF). NASA. Retrieved November 4, 2012.
  27. "NASA Invites Media to View the Morpheus Lander at Kennedy". MEDIA ADVISORY : M12-141. NASA. Retrieved 30 July 2012.
  28. Project Morpheus: Blog. "Moving Forward, Not Starting Over". NASA. Retrieved August 12, 2012.
  29. 1 2 3 "Project Morpheus Tether Test 30". YouTube. NASA. Retrieved August 30, 2013.
  30. "Project Morpheus : Blog: Hard at Work". Project Morpheus. Retrieved 2015-11-19.
  31. 1 2 3 4 "Project Morpheus Tether Test 24". YouTube. NASA. Retrieved June 14, 2013.
  32. 1 2 "Project Morpheus Tether Test 25". YouTube. NASA. Retrieved July 12, 2013.
  33. 1 2 3 "Morpheus Lander Twitter postings on September 24 to 26, 2012". Twitter - Morpheus Lander. NASA. Retrieved September 26, 2013.
  34. "On the road today. Looking forward to flying free in Florida! Don't worry, there will be a cover for the road trip!". Twitter. NASA. Retrieved November 21, 2013.
  35. 1 2 "Project Morpheus Lander Arrives at Kennedy for Testing". NASA. Retrieved December 3, 2013.
  36. 1 2 "Morpheus FreeFlight 9". YouTube - Morpheus Lander. NASA. Retrieved March 12, 2014.
  37. 1 2 "Project Morpheus Free Flight 14". YouTube - Morpheus Lander. NASA. Retrieved May 29, 2014.
  38. "Lunar CATALYST References". NASA website. NASA. Retrieved May 29, 2014.
  39. Jon B. Olansen, PhD; Stephen R. Munday; Jennifer D. Mitchell. "Project Morpheus: Lessons Learned in Lander Technology Development" (PDF). AIAA Space 2013 Conference; 10-12 Sept. 2013; San Diego, CA; United States. American Institute of Aeronautics and Astronautics: SPACE 2013. Retrieved April 24, 2014.
  40. 1 2 3 4 5 6 Devolites, Jennifer, Hart, Jeremy. "Morpheus Vertical Test Bed Flight Testing". 2014 IEEE Aerospace Conference; 1–8 March 2014; Big Sky, MT; United States. Institute of Electrical and Electronics Engineers; New York, NY, United States. Retrieved May 19, 2014.
  41. Lloyd Campbell (July 11, 2014). "Project Morpheus: Flying a test bed for future landers". RocketSTEM (Issue #8 (July 2014)). RocketSTEM Media Foundation, Inc. Retrieved July 12, 2014.
  42. 1 2 Project Morpheus. "Post on November 12, 2014". www.Facebook.com. NASA - National Aeronautics and Space Administration (Facebook Account). Retrieved November 26, 2014.
  43. 1 2 3 "Project Morpheus (Facebook Account)".
  44. 1 2 3 4 "Autonomous Landing and Hazard Avoidance Technology (ALHAT)". NASA. Retrieved November 20, 2012.
  45. 1 2 "Hazard Detection Software for Lunar Landing". Tech Brief. NASA. Retrieved July 2, 2013.
  46. Eric Berger (June 17, 2013). "After failure, NASA mission flies again". Houston Chronicle. Retrieved June 17, 2013.
  47. 1 2 3 Eric Hurlbert; John Patrick Mcmaname; Josh Sooknanen; Joseph W. Studak. "Advanced Development of a Compact 5 - 15 lbf Lox/Methane Thruster for an Integrated Reaction Control and Main Engine Propulsion System" (PDF). NASA. Retrieved July 24, 2013.
  48. 1 2 3 "Project Morpheus Tether Test 25". YouTube. NASA. Retrieved July 25, 2013.
  49. 1 2 "Morpheus Lander posts on July 23, 2013". Facebook. Project Morpheus (Facebook Account). Retrieved July 24, 2013.
  50. 1 2 "Project Morpheus Facebook posts on May 16, 2013". NASA. May 16, 2013. Retrieved May 17, 2013.
  51. "JSC Roundup, April 2011" (PDF). NASA.
  52. "Post on August 4, 2011 around 15:00". Project Morpheus (Facebook Account).
  53. 1 2 "NASA tests Project Morpheus engine" (PDF). Lagniappe (NASA’s John C. Stennis Space Center). 7 (7): 4. July 2012. Retrieved 30 July 2012.
  54. "Twitter postings on December 11, 2013". Twitter - Morpheus Lander. NASA. Retrieved December 18, 2013.
  55. "Post on August 10, 2012 around 13:00". Project Morpheus (Facebook Account). Retrieved August 10, 2012.
  56. "Modular Instrumentation System (MIS)". NASA - JSC Engineering. NASA. Retrieved March 7, 2013.
  57. 1 2 3 Morpheus Ops Lead, Ian Young (@ICYprop). "A Typical Morpheus Test Day". Morpeus website blog. NASA. Retrieved April 24, 2014.
  58. 1 2 "Project Morpheus Tether Test 21". NASA and YouTube. Retrieved May 24, 2013.
  59. 1 2 Keith Cowing (May 18, 2013). "Project Morpheus: Hard Lessons and Lean Engineering". Space Ref. Retrieved May 19, 2013.
  60. 1 2 "Project Morpheus Tether Test 31". YouTube - Project Morpheus. NASA. Retrieved September 19, 2013.
  61. Hillhouse, Jim. "ALHAT – Getting There Safe, Even In The Dark". AmericaSpace. Retrieved February 8, 2013.
  62. Crain, Timothy P.; Brady, Tye (May 13, 2011). "Morpheus GNC Development and Testing" (PDF). NASA. Retrieved February 22, 2013.
  63. Sara McNamara; Guy Schauerhammer; Darby Vicker; Kae Boyles. "Aerodynamic Forces and Moments for the Morpheus Lander Using OVERFLOW" (PDF). NASA. Retrieved February 22, 2013.
  64. "Mission Control Technologies (MCT) Utilized by JSC's Morpheus Lander Project". NASA. Retrieved February 22, 2013.
  65. "Mission Control Technologies (MCT)". NASA. Retrieved February 22, 2013.
  66. David K. Rutishaus; Chirold D. Epp; Edward A. Robertson. "Free-Flight Terrestrial Rocket Lander Demonstration for NASA's Autonomous Landing and Hazard Avoidance Technology (ALHAT) System" (PDF). American Institute of Aeronautics and Astronautics. Retrieved February 22, 2013.
  67. Ron Maglothin, Aaron Brogley. "Lean Development with the Morpheus Simulation Software" (PDF). NASA. Retrieved February 22, 2013.
  68. 1 2 Jon B. Olansen, PhD, Jennifer L. Devolites (January 5, 2015). Project Morpheus: Lean Development of a Terrestrial Flight Testbed for Maturing NASA Lander Technologies (JSC-CN-32448 ed.). NASA Johnson Space Center, Houston, TX 77058. Retrieved April 12, 2015.
  69. "Mission Control Technologies (MCT) Utilized by JSC's Morpheus Lander Project". NASA. Retrieved October 25, 2012.
  70. Jeremy J. Hart, Jennifer D. Mitchell (March 3–10, 2012). "Morpheus Lander Testing Campaign" (PDF). IEEE Conference Publications. IEEE. ISBN 978-1-4577-0556-4. ISSN 1095-323X. Retrieved November 4, 2012.
  71. 1 2 "MorpheusLander Channel webpage on YouTube". NASA and YouTube.
  72. "Post on Project Morpheus's Facebook page on May 10, 2012 at 18:56". NASA and Facebook. May 10, 2012.
  73. Link to video of Morpheus tether test 18, a hover test at the Johnson Space Centre with the ALHAT sensors switched on: Morpheus Tether Test 18.
  74. Project Morpheus Lander, Blog. "Look Out For Those Rocks". NASA. Retrieved April 6, 2012.
  75. "Project Morpheus Twitter posts on May 16, 2013". NASA. May 16, 2013. Retrieved May 17, 2013.
  76. "Project Morpheus Tether Test 22". YouTube. NASA. Retrieved June 6, 2013.
  77. 1 2 "Project Morpheus Tether Test 23". YouTube. NASA. Retrieved June 11, 2013.
  78. "Project Morpheus Facebook posts on and following July 2, 2013". Facebook. NASA. July 2, 2013. Retrieved July 12, 2013.
  79. "Morpheus/ALHAT TT27". YouTube. NASA. Retrieved July 27, 2013.
  80. "Project Morpheus Tether Test 28". YouTube. NASA. Retrieved August 8, 2013.
  81. "Project Morpheus Tether Test 29". YouTube. NASA. Retrieved August 26, 2013.
  82. "Posts on September 24 and 25, 2013". Facebook - Project Morpheus. NASA. Retrieved September 26, 2013.
  83. "Repeated ignition of Morpheus LOX/methane engine on October 29, 2013". Facebook - Project Morpheus. NASA. Retrieved October 29, 2013.
  84. "We did mention that it's wet out here after 2 days of rain! Whatever floats your boat!". Twitter. NASA. Retrieved November 11, 2013.
  85. "Project Morpheus Ground Takeoff and Landing". Facebook - Project Morpheus. NASA. Retrieved November 11, 2013.
  86. "Morpheus TT33". YouTube - Project Morpheus. NASA. Retrieved December 7, 2013.
  87. "Morpheus Flies Free in Kennedy Test". NASA - NASAKennedy. NASA. Retrieved December 11, 2013.
  88. "Morpheus FF03". YouTube - Project Morpheus. NASA. Retrieved December 12, 2013.
  89. "Project Morpheus Free Flight 04". YouTube - Project Morpheus. NASA. Retrieved December 18, 2013.
  90. Link to video of Free Flight 04 as seen by the vehicle: Project Morpheus Free Flight 04 - Vehicle View.
  91. "Project Morpheus Free Flight 05". YouTube - Project Morpheus. NASA. Retrieved January 16, 2014.
  92. "Project Morpheus Free Flight 06". YouTube - Project Morpheus. NASA. Retrieved January 21, 2014.
  93. "Project Morpheus Free Flight 07". YouTube - Project Morpheus. NASA. Retrieved February 10, 2014.
  94. "Morpheus Lander RCS (Feb 14, 2014)". Twitter - MorpheusLander. NASA. Retrieved March 6, 2014.
  95. "Pad Crew for the Lander (Mar 3, 2014)". Twitter - MorpheusLander. NASA. Retrieved March 6, 2014.
  96. "Project Morpheus Free Flight 8". YouTube - Project Morpheus. NASA. Retrieved March 7, 2014.
  97. "Morpheus Completes Tethered Flight With Test of Hazard Avoidance System". YouTube - NASAKennedy. Retrieved March 28, 2014.
  98. "Project Morpheus Free Flight 10". YouTube - Morpheus Lander. NASA. Retrieved April 4, 2014.
  99. "Morpheus Completes Free Flight Test". YouTube - NASAKennedy. NASA. Retrieved April 24, 2014.
  100. "Morpheus Free Flight 12". YouTube - Morpheus lander. NASA. Retrieved May 1, 2014.
  101. "Morpheus Free Flight 13". YouTube - Morpheus lander. NASA. Retrieved May 23, 2014.
  102. Mika McKinnon (November 26, 2014). "The Latest Morpheus Test Flight Cuts Out Before It Even Begins". space.io9.com. Retrieved November 26, 2014.
  103. "Morpheus Tether Test 36". YouTube - Morpheus Lander. NASA. Retrieved December 4, 2014.
  104. Project Morpheus. "Post on November 12, 2014". Facebook. NASA. Retrieved November 26, 2014.
  105. 1 2 Frank Coleman. "GSFC Cryogenic Safety 2013 WFF Safety Awareness Campaign" (PDF). NASA. Retrieved July 9, 2013.
  106. "Project Morpheus - About". Facebook - Project Morpheus. NASA. Retrieved November 11, 2013.
  107. 1 2 "NASA's Morpheus Lander Crashes During First Free Flight Attempt".
  108. "Lunar-lander testing sparks grass fire at Johnson Space Center". KHOU. June 1, 2011.
  109. Hosein, Neesha (November 2011). "Grass fire at Johnson Space Center becomes lesson learned" (PDF). Roundup - Lyndon B. Johnson Space Center: 4. Retrieved May 8, 2013.
  110. Jennifer L. Devolites; Jon B. Olansen, PhD; Stephen R. Munday. "Project Morpheus: Morpheus 1.5A Lander Failure Investigation Results". Conference Paper JSC-CN-29482. AIAA. Retrieved April 18, 2014.
  111. 1 2 Hurlbert, Eric; Morehead, Robert; Melcher, John C.; Atwell, Matt (2016). Integrated Pressure-Fed Liquid Oxygen / Methane Propulsion Systems – Morpheus Experience, MARE, and Future Applications (PDF). NASA CASI. NASA Johnson Space Center.
Wikimedia Commons has media related to Morpheus (lander).
This article is issued from Wikipedia - version of the 11/26/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.