Project 635 Dam

Project 635 Dam
Location of Project 635 Dam in China
Country China
Location Fuhai County, Xinjiang Uighur Autonomous Region
Coordinates 47°14′29″N 88°28′34″E / 47.24139°N 88.47611°E / 47.24139; 88.47611Coordinates: 47°14′29″N 88°28′34″E / 47.24139°N 88.47611°E / 47.24139; 88.47611
Purpose Irrigation, power
Status Operational
Construction began 1998
Opening date 2001
Dam and spillways
Type of dam Embankment, rock-fill with clay core
Impounds Irtysh River
Height 70.6 m (232 ft)
Length 1,900 m (6,200 ft)
Elevation at crest 650 m (2,130 ft)
Reservoir
Total capacity 282,000,000 m3 (229,000 acre·ft)
Normal elevation 645 m (2,116 ft)
Power station
Commission date 2001
Installed capacity 32 MW

The Project 635 Dam (Chinese: "635"水利枢纽工程; pinyin: "635" shuǐlì shūniǔ gōngchéng) is one of the three dams constructed on the Irtysh River in China's Xinjiang Uighur Autonomous Region. The embankment dam is located in Fuhai County, about 56 km east of Beitun. It creates a reservoir (the Project 635 Reservoir, Chinese: "635"水库), which serves as the source of water for the Irtysh–Karamay–Ürümqi Canal.[1]

Water from the reservoir is used for industry, agriculture and power. Construction on the dam began in 1998 and it began to impound its reservoir in 2000. The dam was complete in 2001.[2]

Proposed water transfer from the Burqin River

The Project 635 reservoir is required not only to supply the Irtysh–Karamay–Ürümqi Canal with water, but also to maintain a sufficient amount of water flow in the Irtysh below the dam, for the local agricultural use and ecosystem maintenance. To improve the water balance at the reservoir, the local authorities are envisioning the so-called Project for Bringing Western Water to the East (西水东引工程). The project would involve the construction of a canal whereby water could be transferred from the Burqin Shankou Reservoir on the Burqin River to the Project 635 reservoir on the Irtysh.[3] [4] Even though the Burqin is a tributary of the Irtysh, its natural confluence point with the Irtysh is in Burqin Town (the county seat of Burqin County), which is over 100 km downstream from the Project 635 Dam, and in the absence of the "Bringing Western Water to the East" canal its waters would not be available at the Project 635 location.

Notes

  1. "引额济克工程 (Yin-E-ji-Ke [Bringing Irtysh water to Karamay] Project" (in Chinese). Baidu. Retrieved 25 September 2013.
  2. "635 Hydro Project" (in Chinese). Information Network and Information Center of Changjiang Water Resources Institute. 14 June 2004. Retrieved 25 September 2013.
  3. 额河建管局工程建设和科技发展情况 (Overview of the construction and scientific development projects of the Irtysh Development and Construction Authority), 2010-08-05, by Irtysh Basin Development and Construction Authority (额尔齐斯河流域开发建设管理局)
  4. 引额济克(乌)工程: 635工程 (Bringing Irtysh Water to Help Karamay (Ürümqi) Project (Project 635))
This article is issued from Wikipedia - version of the 9/21/2015. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.