Simplício Hydroelectric Complex

Simplício Hydroelectric Complex
Location of Simplício Hydroelectric Complex in Brazil
Official name Hidrelétrico UHE Simplício
Country Brazil
Location Rio de Janeiro, Minas Gerais
Coordinates 22°2′3″S 43°0′3″W / 22.03417°S 43.00083°W / -22.03417; -43.00083Coordinates: 22°2′3″S 43°0′3″W / 22.03417°S 43.00083°W / -22.03417; -43.00083
Status Operational
Construction began January 2007
Commission date June 2013
Construction cost $2 billion USD[1]
Owner(s) Eletrobrás Furnas
Pumped-storage power station
Upper reservoir Complex contains
Penstocks 3
Lower reservoir five reservoirs
Hydraulic head 80 m (260 ft)
Generating units Main powerhouse: 3 x 101.3 MW (135,800 hp) Francis-type
Anta Dam:
2 x 14.4 MW (19,300 hp) Kaplan-type
Power generation
Nameplate capacity 333.7 MW (447,500 hp)

The Simplício Hydroelectric Complex is located on the Paraíba do Sul river on the border of Rio de Janeiro and Minas Gerais states in Brazil. Supported by the Anta Dam, it transfers water through a 26 kilometres (16 mi) circuit to a downstream power plant. After years of delay and a cost of US$2 billion, the power complex became operational in June 2013.[2][3]

Background

Construction on the complex began in January 2007 after the Brazilian Institute of Environment and Renewable Natural Resources (IBAMA) issued an installation permit. One goal of the project is to reduce environmental impacts created by large reservoirs. The complex's five reservoirs will have a surface area of 15.36 square kilometres (5.93 sq mi).[4] On August 5, 2009, the river was diverted through the Anta Dam's spillway.[5] The rate progress is such that the completion of construction is on schedule for commissioning in 2013.[6] The Anta Dam began to impound its reservoir in late February 2013.[7] All three generators went into operation by early June 2013.[3] The project was completed almost three years behind schedule. Delays were attributed to increased costs, lengthy permit approvals and a court decision which delayed the Anta Reservoir from being filled.[1]

Operation

Water from the Paraíba do Sul is impounded at the 29.5-metre (97 ft) high and 260-metre (850 ft) long roller-compacted concrete Anta Dam before being diverting into a series of eight water channels, four water tunnels and five reservoirs totaling 26 kilometres (16 mi) in length. At the end of the circuit, the water is fed to a power station containing 3 x 101.3 megawatts (135,800 hp) Francis turbines. The Anta Dam itself supports a 28.8 megawatts (38,600 hp) power station with 2 x 14.4 megawatts (19,300 hp)Kaplan turbine-powered generators.[8]

The water diverted by the dam first enters channel C1 which is 1.9 kilometres (1.2 mi) long, 28 metres (92 ft) wide and 8 metres (26 ft) deep. After C1, the water moves into the 1,458-metre (4,783 ft) long tunnel T1 before entering the 1-kilometre (0.62 mi) long channel C2. After C2 and the use of a dike, the water forms the Tocaia reservoir before entering channel C3 which is 565 metres (1,854 ft) long. From C3, water is led into tunnel T2 and then to the 85-metre (279 ft) long channel C4 before reaching tunnel T2A. Water from T2A enters a valley and with the assistance of two dikes, creates Louriçal reservoir. From the reservoir, water enters channel C5 which directs it to the third Calçado reservoir which is partially created by the project's largest dike of 75 metres (246 ft) in height and 400 metres (1,300 ft) in length. The Calçado reservoir uses an outlet works to remove any excess water from the reservoir and help maintain appropriate levels.[8]

Water from the reservoir then moves into the 73-metre (240 ft) long channel C6 which feeds the project's longest tunnel, T3, at 6.03 kilometres (3.75 mi) in length. From T3, water moves into the Antonina reservoir before reaching the 203-metre (666 ft) long channel C7 and then into the Peixe reservoir which is created with the assistance of three dikes. After the reservoir, the water is transferred to intake channel C8 and from there into three 300-metre (980 ft) long penstocks which feed the Simplício Power Plant's three Francis turbines. The penstocks provide 80 metres (260 ft) of hydraulic head and are at a 12.48 percent angle. Once the water is discharged from the power station, it returns to the Paraíba via a 760-metre (2,490 ft) long tailrace channel.[8]

The project was featured on Build It Bigger during a season 8 episode.[9]

References

  1. 1 2 "Brazilian Economy - June 2013" (in Portuguese). Administrators. Retrieved 2 August 2013.
  2. "Delay in operation of HPP Simplicio, Furnas, already exceeds one year" (in Portuguese). Cerpch. Retrieved 8 February 2013.
  3. 1 2 "Plant stands by Simplicio single drop of 115 m" (in Portuguese). PINI Web. 10 July 2013. Retrieved 2 August 2013.
  4. "Water takes a surprising course". Odebrecht. Retrieved 2 January 2011.
  5. "Simplício Hydroelectric Complex carries out re-routing of Paraíba do Sul river". Odebrecht. Retrieved 2 January 2011.
  6. "A strong focus on renewables" (in Portuguese). Ambiente Energia. 28 December 2011. Retrieved 11 January 2012.
  7. Harris, Michael (26 February 2013). "Reservoir Filling Begins at Brazil's Simplicio Hydroelectric Complex". HydroWorld.com. Retrieved 6 May 2013.
  8. 1 2 3 "Sandvik Drill Rigs Tackle Brazilian Hydropower Tunnels". Tunnel Builder. Retrieved 2 January 2011.
  9. "Rio de Janeiro's Power Island". Discovery Channel. Retrieved 2 January 2011.
This article is issued from Wikipedia - version of the 2/18/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.