The Sugarloaf Community Wind Farm is a wind power project in western Maine under development by Endless Energy Corporation. The wind farm is planned to be situated between the Sugarloaf and the Saddleback Maine ski resorts on Redington Pond Range and Black Nubble Mountains.[1]

The 30 wind turbine project is estimated to have a cost of $180 million and would have a capacity of over 90 megawatts, enough to power roughly 40,000 Maine homes.

History

The Sugarloaf Community Wind Farm was derived from the Redington Wind Farm, a previous project proposed by Maine Mountain Power, a joint venture of Endless Energy and Edison Mission Group. In 2007 a permit for this project was denied by the Land Use Regulation Commission although their staff had recommended approval. The developer proposed an alternative project cut down to being only on Black Nubble, which was rejected by LURC a year later.[2]

Public opinion

There has been some controversy over the possibility of a wind farm on the Mount Redington area. Numerous positive environmental effects of wind power have been cited, including pollution avoided from electricity generation from fossil fuels as well as the fact that unlike electricity production from fossil fuel power plants such as coal or petroleum, wind power does not need to use water for cooling.[3] A survey by the Potholm group in 2006 showed 9:1 statewide public support for a wind farm on Redington Mountain (with a margin of error of 5%). The same survey found that 74% of dues paying members of environmental groups in the state were also in favor.

However, the boards of various Appalachian Trail affiliates have opposed the project due to its proximity to the trail.[4] Maine Audubon has also expressed concerns for the fragile environment of the mountains of western Maine.[5] The Natural Resources Council of Maine opposed the full project, but supported the cut down Black Nubble version.[6]

Annexation

At a selectmen's meeting on January 5, 2009, Endless Energy spoke to Carrabassett Valley residents about the possibility of the town to annex the site of the proposed wind farm in the adjacent Redington Township. The town would benefit from the additional property taxes it would receive from the project as well as other benefits of wind farm development such as stable priced power and job creation. The wind farm would benefit from being included in Maine’s expedited wind power permitting zone, as designated by the Governor’s Wind Power Task Force which was put into state law in 2008. The selectmen unanimously voted in favor of sending a Bill into the Maine Legislature.[7]

The annexation bill (SP288)LD741 passed Maine’s Joint Standing Committee on State and Local Government 8-3 on May 11, 2009 with the amendment that all of Redington Township be annexed. To become law it would have required a positive vote from the Senate and House as well as a majority vote in a Carrabassett Valley referendum. For the wind farm to get permits, it would then have then applied to the Department of Environmental Protection instead of the Land Use Regulation Commission.[8][9] On June 1, 2009, the Maine Senate voted against the annexation 29-6, and two days later the House also voted it down.[10]

See also

References

  1. "Sugarloaf Community Wind Farm". Endless Energy Corporation. 2009. Archived from the original on May 16, 2009. Retrieved 2009-05-26.
  2. "Wind project rulings issued. Panel OKs Kibby, rejects Black Nubble". Morning Sentinel. 2008-01-15. Retrieved 2009-05-26.
  3. "How much water do Wind Turbines Use Compared with Conventional Power Plants?". American Wind Energy Association. 2009. Archived from the original on May 16, 2009. Retrieved 2009-05-27.
  4. "Redington Recommendation is Illegal, Say Conservation Groups". Appalachian Mountain Club. 2007-01-18. Retrieved 2009-05-26.
  5. "Redington Recommendation is Illegal, Say Conservation Groups: Intervenors call on land-use commissioners to reject wind-power proposal". Maine Audubon. 2007-01-18. Retrieved 2009-05-26.
  6. "NRCM Endorses Black Nubble Wind Farm: Redington Mountain Would Earn Protection". Natural Resources Council of Maine. 2007-05-07. Retrieved 2009-05-26.
  7. Metzler, Rebekah (2009-04-16). "Redington Plan Draws Crowd". Lewiston Sun Journal. Retrieved 2009-05-26.
  8. "Committee backs Redington annexation". Mainebiz. 2009-05-12. Retrieved 2009-05-26.
  9. "Redington annexation by Carrabassett Valley approved by legislative committee". Daily Bulldog. 2009-05-12. Retrieved 2009-05-26.
  10. "Text and Status for SP288 LD741". Maine Legislature. 2009. Retrieved 2009-06-02.

External links

This article is issued from Wikipedia - version of the 9/12/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.