Kogan Creek Power Station

Kogan Creek Power Station

Viewed from Observation Area
Location of Kogan Creek Power Station in Queensland
Country Australia
Location Brigalow, Queensland
Coordinates 26°54′59″S 150°44′57″E / 26.91639°S 150.74917°E / -26.91639; 150.74917Coordinates: 26°54′59″S 150°44′57″E / 26.91639°S 150.74917°E / -26.91639; 150.74917
Status Operational
Construction began 2004
Commission date 2007
Construction cost A$1.2 billion
Owner(s) CS Energy
Solar field
Type CSP
CSP technology Fresnel reflector
Collectors 14
Total collector area 0.25 km2
Thermal power station
Primary fuel Bituminous coal
Power generation
Units operational 1 X 750 MW
Make and model Siemens
Units cancelled 120 MWth (solar field)
Nameplate capacity 750 MW

The Kogan Creek Power Station is a 750 megawatt coal fired power station owned by CS Energy on the Darling Downs in Queensland.[1] The $1.2 billion plant is situated at Brigalow, in the Surat Basin between Dalby and Chinchilla.

The power station uses supercritical steam technology, which produces lower greenhouse gases emissions per energy unit delivered,[2] and air-cooled surface condensers, which reduces water consumption. The plant consumes 90% less water when compared to conventional power stations through the use of dry cooling technology.[3] The plant runs at 40 per cent efficiency, and requires 42 per cent less fuel input than conventional power stations.

Background

Kogan Creek consists of only one boiler-turbine-generator unit. At 750 MW, it is the largest single unit in Australia. Construction by a consortium led by Siemens commenced in 2004 and was completed in 2007.[4] It was opened by the Queensland Premier Anna Bligh and Minister for Mines and Energy Geoff Wilson on 27 November 2007.[5]

The fuel source is the Kogan Creek coal deposit, which is also owned by CS Energy and will provide 2.8 million tonnes of black coal annually.[6] The coal is delivered to the power station via a 4 km long conveyor belt. The coal mine is operated by Golding Contractors, who has a contract to run the mine until 2018.[7]

The plant 40 per cent efficiency is reached raising the steam pressure to 250 bar at 560 °C.[8]

Carbon Monitoring for Action estimates this power station emits 4.33 million tonnes of greenhouse gases each year as a result of burning coal.[9] The Australian Government has announced the introduction of a Carbon Pollution Reduction Scheme commencing in 2010 which is expected to impact on emissions from power stations. The National Pollutant Inventory provides details of other pollutant emissions, but, as at 23 November 2008, not CO2.

A 28 kilometres (17 mi), 275kV transmission line connects the power station to the National Electricity Market, providing power to Queensland and New South Wales.[1]

Kogan Creek Solar Boost

In April 2011, the failed Kogan Creek Solar Boost project was officially launched. Funding for the project includes a $70 million contribution from CS Energy and a contribution of more than $34 million from the Australian Government. The project was to be constructed by Areva using superheated solar steam technology.[10] Kogan Creek Solar Boost was to be the largest integration of solar technology with a coal-fired power station in the world. Construction started in 2011 and was originally scheduled for completion by 2013.[11][12] Difficulties with the project and commercial issues mean delayed [13][14][15] then aborted to the project.

The project involved the installation of a CLFR solar thermal system capable of generating 44 MW electrical at peak solar conditions.[16][17] Steam from the solar field was to be first further heated and then used to power the intermediate pressure turbine, thereby displacing coal.[18] The 44 MW capacity was not additional to the full 744 MW net capacity of Kogan Creek, rather it is an estimated contribution towards the total generation.[19] The project was expected to reduce carbon emissions by about 35,000 tonnes per year,[10] which is 0.8% of emissions, at a cost of only A$3 per tonne of carbon for the first year's emissions alone.

On 18 March 2016, CS Energy announced that the Solar Boost demonstration project will not be completed.[20][21]

See also

References

  1. 1 2 "Kogan Creek Power Station". CS Energy. Archived from the original on 2008-07-19. Retrieved 2008-11-30.
  2. "A glance beyond renewables". Graham Lovell. 2012-05-15. Retrieved 2014-02-16.
  3. Media Release. Kogan Creek Power Station Project Commences. CS Energy. 20 May 2004. Retrieved on 23 November 2007.
  4. "Kogan Creek Case Study" (PDF). Siemens.
  5. Drought proof generator powers Queensland growth. Ministerial Media Statement. 27 November 2007. Retrieved on 4 December 2007.
  6. Kogan Creek coal-fired power station, Queensland Australia. Retrieved on 23 November 2007.
  7. Golding Contractors Mining and Civil Construction Projects. Golding Contractors. Retrieved on 6 April 2008.
  8. "Advanced 800+ MW Steam Power Plants and Future CCS Options" (PDF). energy.siemens.com. Siemens AG. September 2009. p. 4. Retrieved 17 February 2014.
  9. Kogan Creek Power Plant: Plant overview. Carbon Monitoring for Action. Retrieved on 23 November 2008
  10. 1 2 "$35 Million Government Funding For Kogan Creek Solar Boost Project". Energy Matters. 14 April 2011. Retrieved 14 April 2011.
  11. "Australia plans massive coal-solar combo". United Press International, Inc. 13 April 2011. Retrieved 14 April 2011.
  12. "Kogan Creek Solar Boost Project". CS Energy. Retrieved 14 February 2014.
  13. Parkinson, Giles (7 February 2014). "Commissioning of Kogan Creek 'Solar Boost' project delayed until 2015". Solar Choice. Retrieved 16 February 2014.
  14. "AREVA notes 'difficulties' with Australian solar project". Business Spectator. 7 February 2014. Retrieved 16 February 2014.
  15. "World's biggest solar booster project delayed by "difficulties"". Renew Economy. 6 February 2014. Retrieved 21 March 2016.
  16. "Kogan Creek Solar Boost Project" (PDF). Energy News. 29 (2): 32. June 2011.
  17. "KOGAN CREEK SOLAR BOOST PROJECT, STEP-BY-STEP". Areva Solar. Retrieved 16 February 2014.
  18. "Kogan Creek Solar Boost Project" (PDF). csenergy.com.au. CS Energy. August 2012. Retrieved 17 February 2014.
  19. "Queensland Summary" (XLSX). csenergy.com.au. CS Energy. 2014. Retrieved 6 April 2015.
  20. CS Energy has announced that the Solar Boost demonstration project will not be completed.
  21. (CS Energy) Kogan Creek Solar Boost Project
This article is issued from Wikipedia - version of the 10/27/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.