Montézic Power Station
Montézic Hydroelectric Power Station | |
---|---|
Map showing the Montézic Reservoir. | |
Location of Montézic in the Midi-Pyrénées region of France. | |
Official name | Centrale hydroélectrique de Montézic |
Country | France |
Location | Montézic, Aveyron |
Coordinates | 44°44′16″N 2°38′35″E / 44.73778°N 2.64306°ECoordinates: 44°44′16″N 2°38′35″E / 44.73778°N 2.64306°E |
Status | Operational |
Construction began | 1976 |
Commission date | 1982 |
Operator(s) | EDF |
Pumped-storage power station | |
Upper reservoir | Montézic Reservoir |
Upper res. capacity | 30,000,000 m3 (24,000 acre·ft) |
Penstocks | 2 |
Lower reservoir | Couesques Reservoir |
Lower res. capacity | 56,000,000 m3 (45,000 acre·ft) |
Hydraulic head | 423 m (1,388 ft) |
Pump-generators | 4 reversible Francis turbines |
Power generation | |
Nameplate capacity | 910 MW |
The Montézic Power Station (French: Centrale de Montézic) is a pumped-storage power plant near the commune of Montézic in northern Aveyron, France.[1] Its 910 megawatt capacity ranks it second among France's main pumped-storage facilities,[2][3] and is the only one situated on the Central Massif.[4]
Montézic is a pure pumped-storage plant, which means that its upstream reservoir receives little to no natural inflow of water.[5][6] The station has a weekly time cycle.[7]
History
The power station underwent construction in 1976 and was commissioned in 1982.[8] The following are some key dates from this period:[9]
In August 1976: the power station's access tunnel was bored, and betweenNovember 1977 and July 1978 Grading work for the plant, the connecting tunnels, and the dams was carried out. In July 1979 assembly of the turbine generators took place.
In May 1981 the Etang Dam (Barrage de l'Etang) was completed, and from June to August the upper reservoir was filled.
- October 1981: Completion of the Monnès Dam (Barrage de Monnès).
- January 1982: Filling of the penstock tunnels.
- April 1982: Commissioning of turbine assembly 1
- June 1982: Commissioning of turbine assembly 2
- October 1982: Commissioning of turbine assembly 3
- December 1982: Commissioning of turbine assembly 4
Operation
The power station was built by the electric utility company Électricité de France (EDF, Electricity of France), who operates it under a concession agreement.[10]
Reservoirs
The power station receives water from an upper basin, the Montézic Reservoir, whose active capacity is 30,000,000 cubic meters (24,000 acre feet). Two rock-fill embankment dams form the reservoir:
- the Monnès Dam, 820 meters (2,690 feet) long and 57 m (187 ft) high
- the Etang Dam, 680 m (2,230 ft) long and 30 m (98 ft) high
Under normal conditions, the Montézic Reservoir sits at a 703 m (2,306 ft) elevation and covers a surface area of 245 hectares (0.95 square miles).
Due to the fluctuating water level, the reservoir is unsuitable for leisure activities. In order to remedy this problem, EDF created the Saint Gervais Lake (Lac de Saint Gervais) through the installment of another embankment, providing a stable body of water for the promotion of aquatic tourism.[11]
The lower basin was already in existence as a result of the Couesques Dam, a 70-meter-tall (230 ft) arch dam on the Truyère River built between 1945 and 1950. This reservoir holds a volume of 56,000,000 m3 (45,000 acre·ft).
The Montézic power station utilizes a water volume of 30,000,000 m3 (24,000 acre·ft). If the four turbine generator assemblies are in pump mode, the Couesques Reservoir can be emptied in 40 hours. Both the turbine and pump modes are used on a regular basis.[9]
Penstocks
The penstocks are 5.3 m (17 ft) in diameter and 630 m (2,070 ft) in length. They carry water from the upper reservoir to the power station through the high-pressure tunnel.[12] The water intake, located on the Liaussac Embankment (next to the Monnès Dam), has two sluice gates which allow the high-pressure tunnel to be closed off. Once the water has passed through the turbines, it is evacuated through the 541-meter-long (1,775 ft) low-pressure tunnel towards the Couesques Reservoir.
Power station
The Montézic station lies 400 m (1,300 ft) under the earth, dug out of granite. It has all of the electrical and hydraulic equipment necessary for the operation of its four turbine-pump assemblies, which are each capable of generating 230 MW in turbine mode and 210 MW in pump mode, and permit the transfer of energy from the upper Montézic Reservoir to the lower Couesques Reservoir, and vice-versa. The generator's 18 kV of power are raised to 400 kV by 250 MVA transformers and then sent on to the Ruyères Substation.
The 22 MW static frequency converter (SFC) is used to launch the turbines in pump mode. It performs a progressive increase in speed (from 0 to 428 rpm) as well as the coupling of the pumps to the power grid. Made up of an array of thyristors, the convertor enables a gradual start-up by varying the frequency and thus the speed of the machines. When the synchronization speed is reached, the turbine-pump assembly can be coupled to the grid. The start-up phase is performed dry, with no load.[9]
Each machine has a flow rate of 60 cubic meters per second (2,100 cubic feet per second) in both directions. The pump-turbines are located 60 m (200 ft) below the maximum level of the Couesques Reservoir, which is 40 m (130 ft) below the minimum level. This placement is essential to prevent the creation of depressions or even cavities in the intake tunnel.[13]
As one of France's pumped storage facilities, known as STEP (Station de transfer d'énergie par pompage), Montézic plays a key role in the supply of the French power grid, as it provides a way to quickly restore electricity during a blackout.[14]
See also
- List of power stations in France
- Electricity sector in France
- List of largest hydroelectric power stations
- Hydropower
References
- ↑ "Lot et Truyère : Bruxelles met la pression sur EDF en Aveyron". Centre Press Aveyron
- ↑ "Pumped-storage Power Pants (PSPP)". EDF. Retrieved 3 March 2015.
- ↑ Beno?t Robyns; Bruno Fran?ois; Gauthier Delille; Christophe Saudemont (29 June 2015). Energy Storage in Electric Power Grids. John Wiley & Sons. pp. 26–. ISBN 978-1-84821-611-2. Cite uses deprecated parameter
|coauthors=
(help) - ↑ Jean-Christian Lhomme (27 October 2014). La guerre des watts: Transitions énergétiques & perspectives. Editions Quae. pp. 87–. ISBN 978-2-7592-2230-8.
- ↑ Bernard Multon (7 February 2013). Marine Renewable Energy Handbook. John Wiley & Sons. pp. 11–. ISBN 978-1-118-60329-1.
- ↑ Rock Formations for Dams: Bulletin 88. The Commission. p. 228.
- ↑ "Moyens d'estimer la valeur économique des installations de transfert d'énergie par la simulation mathématique d'exploitation. Application de ces données à l'aménagement et au choix des sites". La Houille Blanche, Number 6-7 (Octobre 1972 P. Gérard
- ↑ "Geological and geographical criteria for underground siting of nuclear reactors". Geostock, P Duffauta
- 1 2 3 "Montézic". Hydroweb (in French). 28 September 2014. Retrieved 23 February 2015.
- ↑ "EDF met en lumière ses nombreuses actions". La Depeche, 14 March 2013
- ↑ Pêche en Viadène (Fishing in Viadène) blog
- ↑ "Hydroélectricité : les élus en terre aveyronnaise". Sud Ouest, 13 July 2013 Jean Toutu
- ↑ "Station de transfert d'énergie par pompage de Montézic" [Montézic Pumped-Storage Power Station]. Hydrelect (in French). 10 October 2013. Retrieved 23 February 2015.
- ↑ Institution of Civil Engineers (Great Britain) (1 January 1990). T. H. Douglas, ed. Pumped Storage: Proceedings of the Conference Organized by the Institution of Civil Engineers at Imperial College of Science, Technology and Medicine, London on 2-4 April 1990. London: Thomas Telford. p. 68. ISBN 978-0-7277-1586-9. Retrieved 13 March 2015.