City Rail Link
City Rail Link | |
---|---|
Overview | |
Type | Commuter rail |
Status | Approved |
Locale | Central Auckland, New Zealand |
Termini |
Britomart Transport Centre Mount Eden Railway Station |
Stations | 4 (incl. termini) |
Operation | |
Character | Underground tunnel |
Technical | |
Line length | 3.5 kilometres (2.2 mi) |
Number of tracks | Double |
Track gauge | 1,067 mm (3 ft 6 in) |
Electrification | 25 kV AC overhead |
City Rail Link layout | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Legend
|
The City Rail Link (CRL) (variously called 'tunnel', 'deviation', or 'loop' in the past) is a rail project in Auckland, New Zealand. The project consists of an electrified, double-track rail tunnel underneath Auckland's city centre, running for approximately 3.5 km between Britomart Transport Centre and the Western Line, connecting just to the west of Mount Eden Railway Station.[1]
Two underground stations will be provided in Auckland's CBD: Aotea Station (located near Aotea Square) and Karangahape Station (located in the vicinity of Karangahape Road). Due to the significant costs and difficulties associated with a project of this size, its planning and funding has been highly controversial.[2]
The current project is an adapted version of previous proposals to improve rail access to Auckland's city centre[3][4] since the 1920s. The CRL was highlighted as the number one transport project in the 2012 Auckland Spatial Plan[5] and has enjoyed strong public support in a number of polls.[6][7] In June 2013 the central government announced its support for the project, albeit with a later construction commencement date of 2020, compared to Auckland Council's preferred start date of 2016.[8][9] The Prime Minister announced in January 2016 that central government funding for main works had been confirmed, allowing Auckland Council to start construction of the main works from 2018, with central funds guaranteed to flow from 2020.[10]
Benefits
The key benefits of the City Rail Link are intended to be:
- Turning Britomart Train Station from a terminus station into a through station,[11] allowing more than twice the existing train capacity through the core of the network (from a maximum of 20 trains per hour, to be reached in 2016, to a projected 48 trains per hour),[12] allowing trains to run every five minutes on the existing suburban lines
- Providing two new train stations in the Auckland CBD, making most of the city centre easily accessible by train rapid transit. This will boost economic activity and development in these areas and relieve projected transport access constraints
- Reducing the duration of trips on the Western Line significantly, by removing the need to deviate to Newmarket and around the east of the CBD[5]
- Allowing lines on opposite sides of the city to be through routed via the tunnel, providing direct crosstown rail connections
- Providing train capacity to allow new lines to be added to the network - including, but not limited to, other potential longer-term projects such as Airport Rail or North Shore Rail
- Doubling the number of Aucklanders who have 30 minutes duration rail access to the CBD[11]
History
1920s Morningside Deviation
Serious planning schemes occurred as early as the 1920s.[4][13] The tunnel was initially estimated at 1.75 miles (2.82 km) length and at £0.6 million.[14] In the 1930s, the Minister of Railways argued that the scheme - then known as the 'Morningside Tunnel' or the 'Morningside Deviation', after the proposed southern portal location - would cost approximately £1 million, with another £1 million required for the electrification of the network. He expressed doubts that the tunnel would ever pay purely from a rail point of view, though he acknowledged that there might be other benefits and wider aspects to take into account.[15]
1970s Rapid Rail System
The 1970s plans envisaged the loop connecting with Newmarket as part of a major rapid transit scheme proposed by Dove-Myer Robinson, mayor of Auckland City at the time. Two main stations were proposed: one downtown in the vicinity of the Queen St/Shortland Street intersection, and a second midtown between Queen St and Mayoral Drive, about halfway between Aotea Square and Albert Park. A third city station was to be built at Karangahape Rd, but this would have been a stop on the western line only.[3] The plan was undermined by Council staff, criticised by academics and opposed by the New Zealand Town Planning Institute,[16] before finally being rejected in 1976 by the Muldoon National government, which considered it to be too costly.[17]
2000s Rail Revival / Britomart
In 2004 Auckland City Council prepared preliminary plans for an underground railway connecting Britomart Transport Centre to the Western Line in the vicinity of Mount Eden Railway Station.[18] The underground link is projected to place the inner city within a 30 minutes travel for around 370,000 people.[19] The proposal included three additional stations: near Aotea Square, Karangahape Rd and the top of Symonds St - bringing most of the CBD within a short walk of a station.[20]
The decision to electrify Auckland's rail network brought the tunnel back into general discussion, while initial feasibility studies for a possible link have already been made.[18] Estimates for the project's cost were around NZ$1.5 billion (or up to $2.4 billion according to other estimates),[4] taking 12–16 years to plan and build.[19][21][22]
On 5 March 2008, Auckland Regional Transport Authority revealed that it had begun preliminary planning for a 3.5 km tunnel between Britomart and Mt Eden, beneath Albert Street and including underground stations near Wellesley St and Karangahape Road,[23] with the Wellesley St station, 18 m under the surface, potentially being larger and seeing more passengers than Britomart (projections of up to 7,700 per peak hour).[19] By October 2008 ONTRACK said that it had reached an agreement in principle with the owners of Westfield Downtown (later rebranded as Downtown Shopping Centre) to allow the tunnel route to thread through the foundations of a proposed redevelopment of the site.[24]
In 2009 and 2010, the discussion on the future tunnel gained much more prominence again, with both candidates for the Mayoralty of the new Auckland Council, John Banks and Len Brown, making the tunnel part of their election platforms. John Banks noted that it attracted cost-benefit returns much higher than many similar-sized roading projects, and would provide much enhanced, integrated access to the city centre.[25] Len Brown also strongly supported the tunnel, and further, a rail connection to Auckland Airport, as part of a package of measures to double public transport patronage within 15 years.[26] However, New Zealand's transport minister in 2010, Steven Joyce, warned Aucklanders not to engage in wishful thinking. The Minister's comments regarding the City Rail Link (and other rail investment), set in context of the government's focus on delivering Roads of National Significance, has been considered politically risky - going against widespread opinion in Auckland in favour of better public transport.[27]
2010s designation and design
In March 2010, KiwiRail/ARTA selected a preferred route with three stations: "Aotea" (beneath Albert St between Victoria St and Wellesley St), "K Road" (beneath Pitt St adjacent to Karangahape Rd) and "Newton" (beneath upper Symonds St between the Khyber Pass/Newton Rd intersection and the New North Rd/Mt Eden Rd intersection), at an estimated cost range of $1 billion to $1.5 billion.[28] In May 2011 the Government noted that after reviewing an initial business case for the project, it was unconvinced of the economic benefits of the tunnel. However, Minister of Transport Steven Joyce noted that he would not stand in the way of Auckland continuing planning and route designation work - if Auckland paid for it.[4] In June 2011 Auckland Council voted to approve $2 million for planning and route protection for the tunnel, with Auckland Transport, rather than KiwiRail, undertaking the process.[29]
In March 2012, Auckland Council decided to bring forward spending from the 2012-2013 budget, in order to continue progress protecting the eventual route. $6.3 million was spent on work including geotechnical surveys, utility and building assessments, contaminated site reports and rail operations modelling and $1.7m towards providing a revised business case, requested by the government.[30][31]
In July 2012, as part of the works around designating the route, Auckland Council released footprints for four stations. This included designation space for a not previously considered station on the current Western Line, just west of Dominion Road. This station would serve as an interchange station for passengers wanting to travel east in the Newmarket direction, in case the tunnel was built without an "Eastern Link" at the southern end that would allow trains exiting it to turn east.[32] The station was later dropped by Auckland Transport and the "Eastern Link" retained in the route protection documents.[1]
In June 2013, the central government announced its support for the project, albeit with a later construction start date of 2020.[8] The government stated it would consider an earlier start date if Auckland's CBD employment and rail patronage growth hit thresholds faster than projected rates of growth.[8]
On 8 July 2013, following the 10-year anniversary of the opening of the Britomart Transport Centre, it was announced that Auckland Council and the new owners of the Downtown Shopping Centre (formerly Westfield Downtown) had agreed to discuss building a section of tunnel under the mall when it is redeveloped in 2016-17. The section would be up to 100 metres long.[33]
On 1 August 2014, Auckland Transport announced a significant design change to the project, dropping the underground Newton Station in favour of an upgraded station at Mt Eden at ground level. This change would save construction costs of $124 million from the capital cost of the City Rail Link project, require fewer properties to be bought by Auckland Transport and in the long term save operational costs, with total savings being over $150 million. In addition, the change would allow the junction between the City Rail Link and the North Auckland Line to be fully grade-separated and enable greater redevelopment potential as the Mount Eden Railway Station site is less affected by heritage buildings and view-shafts.[34][35]
On 27 January 2016, Prime Minister John Key announced in his state of the nation address that central government funding for main works construction of the CRL had been confirmed and this would allow Auckland Council to start to construct the main works from 2018, with central funds guaranteed to flow from 2020.[36] Commentary at the time reflected an opinion that this was a belated agreement to central government funding of the project by the ruling National Party, while the main opposition parliamentary parties (Labour Party, Greens and NZ First) had all been promising immediate construction timetables which were more closely aligned to the plans of the Council.[37]
Business case
One of the most contentious aspects of the CRL is whether it is economically sensible to build it. The results vary widely depending on whether certain ancillary projects are included, whether one assumes economic benefits outside purely transport effects (such as increased land value) and depending on what length of time is assumed for the benefit calculation. In this regard, Council experts have highlighted that NZ calculation methods use a 30-year cut-off (i.e. for evaluation purposes, the tunnel provides no benefit after 30 years, even though much of Auckland's earlier rail and road infrastructure already serves for much longer than that). In comparison, if using evaluation periods of 50 years (used in Australia), or 60 years (used in the UK), the total project benefits for the city rail link have been estimated as up to 6 times higher than with the 30 year time frame.[38]
The "City Centre Future Access Study" (CCFAS) was prepared by Auckland Transport and released in December 2012. The CCFAS analysed a number of different ways of improving access to Auckland's city centre and concluded that the CRL was essential, noting that bus-only investment will provide for short-term benefits but in some cases will be ‘worse than doing nothing’ for private vehicle travel times in the longer term.[39] In July 2013, the Transport Agency's board agreed that transport projects were to be assessed for a 40-year evaluation period, but also reduced the discount rate from 8% to 6%.[40]
Cost
An estimated cost of $2.86 billion is often quoted for the project,[41] but this cost was inflated out to the year of construction. The cost of the project in 2010 was $2.311 billion.[42] That price also included not only the tunnel link with three stations (Newton station later dropped), but additional trains, duplication of the Onehunga Branch to two lines and other small improvements to Auckland's rail network. These additional items are intended to further increase the capacity of Auckland's rail network when the rail link opens, the main benefit posed by the project.[5]
In September 2016, the government formally confirmed its intention to fund its proposed share of 50% of the City Rail Link. The cost of the City Rail Link was then re-estimated to be between $2.8 and $3.4 billion, subject to tenders for remaining contracts.[43]
Proposed timeline
In February 2012, Auckland Council published the following proposed project timeline for the City Rail Link:
- 2010 Initial study for CRL project and potential route for protection
- 2011 Review of initial study; further feasibility investigations; project team established
- 2012 Confirm route for CRL
- 2013 Notice of Requirement (NOR) and consent applications; property purchase
- 2014 Begin tender process for project
- 2015–20 Construction
- 2020/21 CRL opens[44]
Proposed construction methods
The City Rail Link will be constructed using both cut-and-cover and tunnel boring machine (TBM) methods depending on the location of construction. The ground through which the tunnels will be built varies between rock and soft soil, and with a variation in depth to natural ground level of between 40 metres and 0 metres.[45] Cut and cover construction will occur around the existing Mount Eden Railway Station and in the suburb of Eden Terrace, forming the junction of the City Rail Link to the North Auckland Line. North of the junction, twin bored tunnels will then extend as far as Mayoral Drive. Another section of cut and cover tunnel will then extend north underneath Albert Street, before turning east to head underneath the redeveloped Downtown Shopping Centre and into Britomart.[46]
It is expected that the TBM will commence boring the first tunnel from a construction site close to New North Road in Eden Terrace. Once the TBM reaches Mayoral Drive it will be disassembled and taken back to Eden Terrace where it will be reassembled to bore the second tunnel.[46]
Some landowners around Albert Street, including the Ministry of Justice which owns and operates the Auckland District Court on Albert Street, have expressed their concern that construction of the cut and cover tunnel would disrupt foot and vehicular traffic along Albert Street over a period of two years with several intersections along the street being closed for up to 18 months. Similarly, the Department of Corrections has also expressed concern that grade-separating the Normanby Road level crossing (as part of the cut and cover works at the southern end of the project) would cut off access to Mount Eden Prisons.[47]
Construction
On 7 April 2015, two construction consortia[45] were awarded the contracts to start the first construction phase of the city rail link.[48] Construction of the early works package between Britomart and Wyndham Street will begin in October 2015.[49]
The Downer joint venture (Downer NZ and Soletanche Bachy) has been chosen to design the rail link work through and under Britomart Station and Queen St to Precinct Properties’ Downtown Shopping Centre site, with construction likely to start early 2016.[48]
The Connectus consortium (McConnell Dowell and Hawkins) will construct the cut and cover tunnels under and along Albert St from Customs St to Wyndham St. The work is likely to start in October 2015 with the relocation of a major stormwater line in Albert St between Swanson and Wellesley Sts.[48]
Construction of these sections of the city rail link tunnels will coincide with Precinct Properties redevelopment of the Downtown Shopping Centre site, due to open by mid-2019.[48][50][51]
The Downtown Shopping Centre was closed on 28 May 2016 and by 23 November had been demolished. It will be replaced with a 36-storey skyscraper which will include a new shopping centre in the lower levels. Auckland Council and proprietors Precinct Properties struck a deal to include tunnels for the City Rail Link directly underneath the premises.[52][53]
Future phases
The main works are expected to start in 2018 with completion in 2023.[49]
Public opinion
A public opinion poll published on 27 June 2012 found 63% of Aucklanders surveyed are in favour of the tunnel, 29% were against it and 8% don't care. The poll was conducted by Research New Zealand.[54]
Another poll in November showed similar support amongst Aucklanders at 64%.[7] Only 14% overall opposed the building of the rail link; 18% are neutral. Support was lowest in those areas not served directly by rail. The same number of those who support it want it built as soon as possible, while 22% of supporters want it built by 2020. Over 50% of respondents wanted the central Government to contribute significantly to the cost of the project, with 30% of respondents overall supporting road tolling to pay for the project. One quarter of respondents overall supported "targeted rates".[55]
See also
References
- 1 2 "The CRL route". Auckland Transport. Retrieved 22 February 2014.
- ↑ Editorial. "If mayor can sell rail study, Govt should stand aside". New Zealand Herald. New Zealand Herald. Retrieved 22 February 2014.
- 1 2 Reid, Nicolas. "An Auckland that could have been: the 1972 Auckland Rapid Rail Transit Plan". TransportBlog.co.nz. Retrieved 23 February 2014.
- 1 2 3 4 Dearnaley, Mathew (4 June 2011). "Stuck in traffic". The New Zealand Herald. Retrieved 12 July 2011.
- 1 2 3 Auckland Council. "The Auckland Plan". Retrieved 22 February 2014.
- ↑ Dearnaley, Mathew (14 July 2011). "Rail-loop support swamps backing for road link". The New Zealand Herald. Retrieved 15 July 2011.
- 1 2 "Aucklanders back Brown's rail plans". 3 News NZ. 19 November 2012.
- 1 2 3 "Kick-starting Auckland transport projects". New Zealand National Party. 29 June 2013.
- ↑ Rudman, Brian. "Brown hands PM an election poser". New Zealand Herald. Retrieved 22 February 2014.
- ↑
- 1 2 "City Rail Link Moves Ahead". Our Auckland (Auckland Council newsletter). August 2012.
- ↑ "Len Brown: Rail link a positive after missed opportunities". The New Zealand Herald. Retrieved 20 January 2016.
- ↑ History of Auckland City - Chapter 4 (from the Auckland City Council website. Accessed 2008-06-07.)
- ↑ "Auckland City Development Works - Cost to Government". Evening Post. 9 November 1928. p. 8. Retrieved 29 June 2011.
- ↑ "Cost of £2,000,000". Evening Post. 29 September 1936. p. 10. Retrieved 18 June 2011.
- ↑ Mees, Paul (2012). Transport for Suburbia: Beyond the Automobile Age. Earthscan. p. 27. ISBN 9781849774659.
- ↑ Chapter 2 - City Takes Control 1959-1995 (from the Britomart Transport Centre website. Accessed 2008-09-06.)
- 1 2 Auckland’s rail network tomorrow: 2016 to 2030 Archived 28 September 2007 at the Wayback Machine. (PDF) (from the ARTA, August 2006)
- 1 2 3 Huge underground rail station in mid-town plan - The New Zealand Herald, Friday 1 August 2008
- ↑ Dye, Stuart. "Underground rail link feasible, says study". New Zealand Herald. New Zealand Herald. Retrieved 22 February 2014.
- ↑ Dearnaley, Mathew (21 May 2007). "$1b Auckland rail upgrade powers ahead". The New Zealand Herald. Retrieved 22 September 2011.
- ↑ Following the money - e.nz magazine, IPENZ, January/February 2007
- ↑ Mathew Dearnaley (5 March 2008). "$1b loop tunnel plan to unlock Britomart". The New Zealand Herald. Retrieved 2008-03-05.
- ↑ Tunnel deal brings rail loop step closer - The New Zealand Herald, 2008-10-14
- ↑ "John Banks: Rail loop to unlock the potential of Auckland". The New Zealand Herald. 12 October 2009. Retrieved 21 February 2010.
- ↑ Orsman, Bernard (31 August 2009). "Brown vows he'll unite, not divide". The New Zealand Herald. Retrieved 21 February 2010.
- ↑ Dearnaley, Mathew (6 November 2009). "National one year on: Beware the backlash of frustrated commuters". The New Zealand Herald. Retrieved 21 February 2010.
- ↑ Dearnaley, Mathew (11 March 2010). "Experts pinpoint best tunnel route". The New Zealand Herald. Retrieved 11 March 2010.
- ↑ "Auckland Council presses on with rail project". TVNZ. 28 June 2011. Retrieved 29 June 2011.
- ↑ Auckland Council Media release, City Rail Link work accelerated
- ↑ Auckland Council Media release, Progress on City Rail Link welcomed
- ↑ "Sprawling footprints for underground stations". The New Zealand Herald. 31 July 2012. Retrieved 31 July 2012.
- ↑ "Section of city rail tunnel could be built earlier". Radio New Zealand. 8 July 2013.
- ↑ "Cost down, benefits up from City Rail Link design change". Auckland Transport. Retrieved 3 August 2014.
- ↑ "Cost down, benefits up from City Rail Link design change" (Press Release). Scoop.co.nz. Auckland Transport. 1 August 2014. Retrieved 3 August 2014.
- ↑ "Speech to Auckland Chamber of Commerce". 27 January 2016.
- ↑ "Fran O'Sullivan: Key's reluctant fillip two years too late". The New Zealand Herald. Retrieved 7 February 2016.
- ↑ Cooper, Geoff (6 November 2012). "The value of infrastructure: multiply that by six". Chief Economist, Auckland Council via New Zealand Herald.
- ↑ "Warnings of Auckland transport network crisis". Auckland Council. Retrieved 23 February 2014.
- ↑ "Economic Evaluation Manual". NZ Transport Agency. 16 March 2015. Retrieved 16 May 2015.
- ↑ "CRL Updates and Resources". Auckland Transport. Retrieved 12 March 2014.
- ↑ "Business Case - Auckland CBD Rail Link" (PDF). APB&B. p. 49. Retrieved 12 March 2014.
- ↑ Orsman, Bernard (14 September 2016). "Exclusive: Auckland's City Rail Link cost blows out to up to $3.4 billion". The New Zealand Herald. Retrieved 2016-09-14.
- ↑ Overview of the City Rail Link project, Auckland Transport Feb 2012
- 1 2 "Aucklands missing link". Contractor magazine. Retrieved 12 June 2015.
- 1 2 "Project delivery & construction". Auckland Transport. Retrieved 3 August 2013.
- ↑ Dearnaley, Matthew (7 August 2013). "Auckland rail plan sparks traffic fear". The New Zealand Herald. Retrieved 7 August 2013.
- 1 2 3 4 "City rail link to become a reality". NBR. Retrieved 7 April 2015.
- 1 2 "Project delivery & construction". Auckland Transport. Retrieved 1 June 2015.
- ↑ "Precinct-gears-up-for-Auckland-mega-project". Stuff. Retrieved 25 Feb 2015.
- ↑ "New $550m downtown tower for Auckland unveiled". NZHerald. Retrieved 25 Feb 2015.
- ↑ Catherine Gaffaney (22 May 2016). "Last week for shoppers at Auckland downtown mall". NZ Herald.
- ↑ "Watch $850m project: preparing for NZ's biggest commercial development". NZ Herald. 23 November 2016. Retrieved 23 November 2016.
- ↑ Kelsey Fletcher (27 June 2012). "Aucklanders back rail plans". Auckland Now.
- ↑ "64% of Aucklanders support $2.5 billion city rail link project". HorizonPoll. 19 November 2012. Retrieved 12 November 2012.
External links
- City Rail Link (official Auckland Transport website)
- Auckland Transport Blog (City Rail Link page)
- Campaign for Better Transport Forum (City Rail Link Topic Page)