Glasgow East End Regeneration Route

The Glasgow East End Regeneration Route (EERR) is a new road in the East End of Glasgow, Scotland. Currently under construction, the first phase was opened in 2011 with the second phase opened in mid-2012; these two phases now officially known as the A728 Clyde Gateway. A third phase from the Parkhead Bypass to Provan (M8/M80) is proposed.

History

The history of the route goes back to the Glasgow Inner Ring Road (IRR) project of the 1960s. Owing largely to public opposition, only the northern and western flanks of this were ever built (what is now the central section of the M8). With the resultant chronic traffic congestion on the M8, only recently has the southern flank, the M74 Completion, finally opened after much local opposition. The construction of the EERR link will provide an 'inner circle' connecting the new section of M74 at Polmadie Road with the M8 at Provan.

Route

The route of the EERR was planned as early as 1965 by the then Glasgow Corporation after the Glasgow Inner Ring Road proposals originating from the Bruce Report, and was originally a continuation of the Stirling Motorway (which would be realised as the M80) which would have run directly south beyond the interchange with the Monkland Motorway (the present-day M8) at Provan Gas Works. This road would have driven south towards the extended South Link Motorway (now the M74) and would have served as an "outer ring" for the city. As the appetite for further inner urban motorway developments waned in the 1970s following the backlash when the city centre section of the IRR was built in the late 1960s, the route evolved into an urban thoroughfare instead.

The M80, when eventually built in the early 1990s, now terminated at the Provan Gas Works interchange, whilst the Parkhead bypass, constructed in 1988 as part of the Parkhead Forge shopping development, was effectively the first section of the EERR. From Parkhead, the road would cut northward, through Hogarth Park, a former railway embankment now used as public open space. The new road would run between Haghill and Carntyne, under Edinburgh Road and Cumbernauld Road continuing along the old Caledonian Railway "Switchback" line to the M8/M80 junction at Provan.

The southern section of the EERR runs from junction 1A of the now-completed M74 extension at Polmadie to Shawfield Stadium, over Rutherglen Bridge and past Dalmarnock railway station, before linking up with the Parkhead bypass. This section was completed in April 2012.

Progress

A planning application was submitted in October 2005, but the 'winning' of being Host City for the 2014 Commonwealth Games has provided the necessary impetus. Phase 1, from Polmadie Road to Shawfield Stadium opened in April 2007 as part of the Oatlands development and was named the Clyde Gateway.[1]

Phase 2 opened in April 2012.[1] The route extends the Clyde Gateway, crossing the River Clyde at Rutherglen Bridge, passing Dalmarnock railway station and the new stadia district before joining the existing road network at the Forge Retail Park.[1]

Construction of phase 3, linking north from Parkhead Bypass to the M8 at Provan along a disused railway line, is due to commence after the 2014 Commonwealth Games.[1]

References

  1. 1 2 3 4 "New £25m Clyde Gateway road opens in Glasgow". BBC News. BBC. 26 April 2012. Retrieved 24 June 2012.

Coordinates: 55°51′19″N 4°12′13″W / 55.8553°N 4.2037°W / 55.8553; -4.2037

This article is issued from Wikipedia - version of the 12/4/2014. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.