Martin Next Generation Solar Energy Center
Martin Next Generation Solar Energy Center | |
---|---|
Location of Martin Next Generation Solar Energy Center in Florida | |
Country | United States |
Location | Martin County, Florida |
Coordinates | 27°03′11″N 80°33′00″W / 27.053°N 80.550°WCoordinates: 27°03′11″N 80°33′00″W / 27.053°N 80.550°W |
Status | Operational |
Construction began | December 2008 |
Commission date | December 2010 |
Construction cost | $141 million |
Owner(s) | FPL |
Solar field | |
Type | CSP |
CSP technology | Parabolic trough |
Collectors | 6,864 (192,192 mirrors) |
Site area | 500 acres (202 ha) |
Power generation | |
Nameplate capacity | 75 MW |
Capacity factor | 24% |
Planned generation | 155 GWh |
Website http://www.fpl.com/environment/solar/martin.shtml |
Martin Next Generation Solar Energy Center is the solar parabolic-trough component of an integrated solar combined cycle 1150 MW plant, in western Martin County, Florida, just north of Indiantown, built by Florida Power & Light Company (FPL). The ISCC plant is part of the Martin Plant site which consists of 5 units. Unit 1 & Unit 2 are 800 MW steam electric generating units that use natural gas and low-sulfur residual oil. Unit 3 & Unit 4 are 500 MW natural gas-fired combined cycle units. Unit 8 is a natural gas fired 4-on-1 combined cycle unit with a nominal capacity of 1150 MW. Light oil is used as backup. Unit 8, placed into commercial operation in 2005, is integrated with the solar plant. Unit 8 features four 170 MW gas turbines, one 470 MW steam turbine, and a single condenser and cooling tower[1] .[2] The single solar field circuit heats 4 steam generators, after each gas turbine. The Martin solar thermal facility is designed to provide steam for FPL's existing Martin Unit 8 combined cycle unit, thus reducing FPL's use of natural gas. No additional capacity (MW) will result from the operation of the solar thermal facility. The Solar Energy Center has an array of approximately 190,000-mirror parabolic troughs on about 500 acres (202 ha) of the Martin County plant.[3] The solar collectors feed heat to the existing steam plant, generating electricity at a rate of 155,000 MWh per year.[4] The 2012 solar-derived production was about 89,000 MWh of power, according to records filed with the state’s Public Service Commission, which was 42% less than projected when the plant got approval.[5] Lauren Engineers & Constructors (Abilene, TX) was the EPC contractor for the project.[6] Construction began in 2008[7] and was completed by the end of 2010.[8]
FPL expects the $476 million[9] solar plant to reduce the combined-cycle power plant's natural gas consumption by 1.3 billion cubic feet (37 million m³) per year.[9] Over the 30-year life of the project, this is expected to save $178 million in fuel cost[10] and reduce carbon emissions by 2.75 million tons.[9]
Excess pressure and a release of operating fluid led to the plant being shut down for four months in 2011 for cleanup and testing.[11]
As of 2016, no additional concentrated solar plants are planned for Florida, although in 2007 FPL had planned on building a 300 MW fresnel solar thermal plant.[12]
Production
Year | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2011 | 2,868 | 4,641 | 9,249 | 2,891 | 3,357 | 114 | -121 | -121 | 3,640 | -119 | 2,668 | 0 | 29,067 |
2012 | 5,017 | 2,921 | 9,915 | 12,018 | 9,555 | 9,100 | 11,001 | 7,541 | 6,169 | 7,146 | 3,956 | 3,999 | 88,338 |
2013 | 4,388 | 7,288 | 8,883 | 7,254 | 12,784 | 14,352 | 12,872 | 10,675 | 8,227 | 9,372 | 2,522 | 3,264 | 101,881 |
2014 | 4,632 | 8,055 | 10,500 | 11,950 | 13,344 | 9,944 | 11,009 | 12,322 | 11,236 | 16,884 | 5,971 | 8,629 | 124,476 |
2015 | 4,730 | 437 | 8,791 | 9,877 | 15,155 | 15,571 | 17,349 | 14,827 | 7,468 | 6,139 | 3,809 | 1,950 | 106,103 |
2016 | 2,222 | 5,510 | 5,728 | 11,479 | 13,962 | 38,901 | |||||||
Total | 488,766 |
See also
- List of concentrating solar thermal power companies
- List of photovoltaic power stations
- List of solar thermal power stations
- Renewable energy in the United States
- Renewable portfolio standard
- Solar power in the United States
References
- ↑ "Case Study: Martin County Expansion Project (2004)". GEA. Retrieved 2013-05-18.
- ↑ "Draft Permit - Florida Department of Environmental Protection" (PDF). FDEP. Retrieved 2013-05-19.
- ↑ Mayfield, Jim (2008-12-03). "World's first hybrid solar power facility breaks ground in Martin County". TCPalm.com. Scripps Interactive Newspapers Group. Retrieved 2009-05-26.
- ↑ "Martin Next Generation Solar Energy Center FAQs". FPL. Retrieved 2009-05-26.
- ↑ Samples, Eve (2013-03-10). "FPL's Martin solar energy center still struggling to meet its targets". TCPalm.com. Scripps Interactive Newspapers Group. Retrieved 2013-05-19.
- ↑ "75-MW CSP Plant to be Built in Florida". RenewableEnergyWorld.com. March 27, 2009. Retrieved 2009-08-01.
- ↑ "FPL Breaks Ground on First Hybrid Solar Plant". RenewableEnergyWorld.com. December 5, 2008. Retrieved 2009-05-26.
- ↑ Vo, Danny (January 10, 2011). "Florida utilities lay plans for solar projects in 2011". CoolerPlanet.com. Retrieved 2011-01-28.
- 1 2 3 Mouawad, Jad (March 4, 2010). "The Newest Hybrid Model". The New York Times. Retrieved 2011-01-28.
- ↑ Patel, Julie (January 28, 2011). "FPL's estimates on solar costs customers pay questioned". South Florida Sun-Sentinel. Retrieved 2011-01-28.
- ↑ Major spill at FPL solar plant gets glossed over
- ↑ Big Solar Thermal Power Plants Planned for Florida, California
- ↑ "Martin Next Generation Solar Energy Center, monthly". Electricity Data Browser. Energy Information Administration. Retrieved March 19, 2016.
External links
- "The Cost of Solar Electricity at the Martin Next Generation Solar Energy Center". Gerson Lehrman Group. March 14, 2010. Retrieved 2011-01-28.