Martin Next Generation Solar Energy Center

Martin Next Generation Solar Energy Center
Location of Martin Next Generation Solar Energy Center in Florida
Country United States
Location Martin County, Florida
Coordinates 27°03′11″N 80°33′00″W / 27.053°N 80.550°W / 27.053; -80.550Coordinates: 27°03′11″N 80°33′00″W / 27.053°N 80.550°W / 27.053; -80.550
Status Operational
Construction began December 2008
Commission date December 2010
Construction cost $141 million
Owner(s) FPL
Solar field
Type CSP
CSP technology Parabolic trough
Collectors 6,864 (192,192 mirrors)
Site area 500 acres (202 ha)
Power generation
Nameplate capacity 75 MW
Capacity factor 24%
Planned generation 155 GWh
Website
http://www.fpl.com/environment/solar/martin.shtml

Martin Next Generation Solar Energy Center is the solar parabolic-trough component of an integrated solar combined cycle 1150 MW plant, in western Martin County, Florida, just north of Indiantown, built by Florida Power & Light Company (FPL). The ISCC plant is part of the Martin Plant site which consists of 5 units. Unit 1 & Unit 2 are 800 MW steam electric generating units that use natural gas and low-sulfur residual oil. Unit 3 & Unit 4 are 500 MW natural gas-fired combined cycle units. Unit 8 is a natural gas fired 4-on-1 combined cycle unit with a nominal capacity of 1150 MW. Light oil is used as backup. Unit 8, placed into commercial operation in 2005, is integrated with the solar plant. Unit 8 features four 170 MW gas turbines, one 470 MW steam turbine, and a single condenser and cooling tower[1] .[2] The single solar field circuit heats 4 steam generators, after each gas turbine. The Martin solar thermal facility is designed to provide steam for FPL's existing Martin Unit 8 combined cycle unit, thus reducing FPL's use of natural gas. No additional capacity (MW) will result from the operation of the solar thermal facility. The Solar Energy Center has an array of approximately 190,000-mirror parabolic troughs on about 500 acres (202 ha) of the Martin County plant.[3] The solar collectors feed heat to the existing steam plant, generating electricity at a rate of 155,000 MWh per year.[4] The 2012 solar-derived production was about 89,000 MWh of power, according to records filed with the state’s Public Service Commission, which was 42% less than projected when the plant got approval.[5] Lauren Engineers & Constructors (Abilene, TX) was the EPC contractor for the project.[6] Construction began in 2008[7] and was completed by the end of 2010.[8]

FPL expects the $476 million[9] solar plant to reduce the combined-cycle power plant's natural gas consumption by 1.3 billion cubic feet (37 million m³) per year.[9] Over the 30-year life of the project, this is expected to save $178 million in fuel cost[10] and reduce carbon emissions by 2.75 million tons.[9]

Excess pressure and a release of operating fluid led to the plant being shut down for four months in 2011 for cleanup and testing.[11]

As of 2016, no additional concentrated solar plants are planned for Florida, although in 2007 FPL had planned on building a 300 MW fresnel solar thermal plant.[12]

Production

Solar generation (MWh) of Martin Next Generation Solar Energy Center [13]
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
2011 2,868 4,641 9,249 2,891 3,357 114 -121 -121 3,640 -119 2,668 0 29,067
2012 5,017 2,921 9,915 12,018 9,555 9,100 11,001 7,541 6,169 7,146 3,956 3,999 88,338
2013 4,388 7,288 8,883 7,254 12,784 14,352 12,872 10,675 8,227 9,372 2,522 3,264 101,881
2014 4,632 8,055 10,500 11,950 13,344 9,944 11,009 12,322 11,236 16,884 5,971 8,629 124,476
2015 4,730 437 8,791 9,877 15,155 15,571 17,349 14,827 7,468 6,139 3,809 1,950 106,103
2016 2,222 5,510 5,728 11,479 13,962 38,901
Total 488,766

See also

References

  1. "Case Study: Martin County Expansion Project (2004)". GEA. Retrieved 2013-05-18.
  2. "Draft Permit - Florida Department of Environmental Protection" (PDF). FDEP. Retrieved 2013-05-19.
  3. Mayfield, Jim (2008-12-03). "World's first hybrid solar power facility breaks ground in Martin County". TCPalm.com. Scripps Interactive Newspapers Group. Retrieved 2009-05-26.
  4. "Martin Next Generation Solar Energy Center FAQs". FPL. Retrieved 2009-05-26.
  5. Samples, Eve (2013-03-10). "FPL's Martin solar energy center still struggling to meet its targets". TCPalm.com. Scripps Interactive Newspapers Group. Retrieved 2013-05-19.
  6. "75-MW CSP Plant to be Built in Florida". RenewableEnergyWorld.com. March 27, 2009. Retrieved 2009-08-01.
  7. "FPL Breaks Ground on First Hybrid Solar Plant". RenewableEnergyWorld.com. December 5, 2008. Retrieved 2009-05-26.
  8. Vo, Danny (January 10, 2011). "Florida utilities lay plans for solar projects in 2011". CoolerPlanet.com. Retrieved 2011-01-28.
  9. 1 2 3 Mouawad, Jad (March 4, 2010). "The Newest Hybrid Model". The New York Times. Retrieved 2011-01-28.
  10. Patel, Julie (January 28, 2011). "FPL's estimates on solar costs customers pay questioned". South Florida Sun-Sentinel. Retrieved 2011-01-28.
  11. Major spill at FPL solar plant gets glossed over
  12. Big Solar Thermal Power Plants Planned for Florida, California
  13. "Martin Next Generation Solar Energy Center, monthly". Electricity Data Browser. Energy Information Administration. Retrieved March 19, 2016.
This article is issued from Wikipedia - version of the 8/25/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.